12.04.2015 Views

3720 - Board of Claims

3720 - Board of Claims

3720 - Board of Claims

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

that he is aware delays might be incurred in the performance <strong>of</strong> work on this<br />

project as a result <strong>of</strong> work being performed or that will be performed on such<br />

facilities by their owners.<br />

It is further understood that, notwithstanding assistance <strong>of</strong> any kind and extent<br />

that might be provided by the department, the contractor, in every instance, bears<br />

the ultimate responsibility in resolving all disputes <strong>of</strong> every kind with the owners<br />

<strong>of</strong> such facilities. The contractor agrees to save and hold the Department<br />

harmless from liability for all delays, interference and interruptions that might<br />

arise during the performance <strong>of</strong> the work on this project as a result <strong>of</strong> work being<br />

or that will be performed on such publicly or privately-owned facilities.<br />

Ex. P-8 at p. 5.<br />

33. The “Utilities” section <strong>of</strong> the Special Provisions <strong>of</strong> the Contract also provided that<br />

the contractor had the following duties regarding the relocation:<br />

Cooperate with the public utility companies and local authorities in the placement,<br />

replacement, relocation, adjustment or reconstruction <strong>of</strong> their structures and<br />

facilities during construction.<br />

Contact all utility representatives at least fifteen calendar days prior to starting<br />

operations.<br />

Exs. P-2B, P-8 at p. 34.<br />

34. Because we have found, as a matter <strong>of</strong> fact, that Intercounty fully cooperated with<br />

the utility companies to relocate the utility poles and wires on the Project in all material respects,<br />

we hold that Intercounty met its duty to cooperate with the utility companies to the extent required<br />

under the terms <strong>of</strong> the Contract and the 408 Specifications incorporated therein, including the<br />

requirements in Paragraph 6 and in the “Utilities” section <strong>of</strong> the Special Provisions <strong>of</strong> the Contract<br />

and in Sections 102.05, 105.06(a) and 105.06(b). Ex. P-8; 408 Specifications §§ 102.05, 105.06(a)<br />

and 105.06(b).<br />

35. Because we have found, as a matter <strong>of</strong> fact, that Intercounty’s participation in the<br />

pre-construction meeting <strong>of</strong> June 5, 2001 (immediately prior to PennDOT’s execution <strong>of</strong> the<br />

Contract) and the subsequent pre-job meeting on June 11, 2001 with the utility companies affected<br />

by the Project, and the discussions regarding the relocation <strong>of</strong> said utility poles and wires on the<br />

Project at those meetings, reasonably complied in all material respects with the initial requirements<br />

<strong>of</strong> contacting the affected utility companies on the Project, as set forth in the Contract and 408<br />

Specifications (including those set forth in Paragraph 6, in the “Utilities” section <strong>of</strong> the Special<br />

Provisions <strong>of</strong> the Contract, and in the 408 Specifications §§ 102.05, 105.06(a) and 105.06(b)), we<br />

hold that Intercounty met its initial duty to contact the utility companies and make arrangements<br />

for pole and wire relocations as required by the Contract. Ex. P-8; 408 Specifications §§ 102.05,<br />

105.06(a) and 105.06(b).<br />

52

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!