V. DAMAGE SUMMARY<br />
For all the foregoing reasons, the <strong>Board</strong> grants judgment against PennDOT and in favor<br />
<strong>of</strong> Intercounty in the following amounts:<br />
1. Delay Damages<br />
Extended Field Conditions $ 12,470.02<br />
Extended Maintenance and Protection <strong>of</strong> Traffic $ 14,225.79<br />
Material Cost Escalation $144,945.00<br />
Total Delay Damages (including markup $171,640.81<br />
for supervision, overhead and pr<strong>of</strong>it)<br />
2. Disruption Damages $405,671.00<br />
3. Additional Cost <strong>of</strong> Undercutting $ 13,571.25<br />
4. Rideability Incentive -0-<br />
5. Rehandling <strong>of</strong> Stockpiled Materials -0-<br />
6. Attorney’s Fees and Costs -0-<br />
TOTAL DAMAGES $590.883.06<br />
Plus Pre-judgment Interest (28.67%) + $169,406.17<br />
TOTAL $760,289.23<br />