V. DAMAGE SUMMARY<br />

For all the foregoing reasons, the <strong>Board</strong> grants judgment against PennDOT and in favor<br />

<strong>of</strong> Intercounty in the following amounts:<br />

1. Delay Damages<br />

Extended Field Conditions $ 12,470.02<br />

Extended Maintenance and Protection <strong>of</strong> Traffic $ 14,225.79<br />

Material Cost Escalation $144,945.00<br />

Total Delay Damages (including markup $171,640.81<br />

for supervision, overhead and pr<strong>of</strong>it)<br />

2. Disruption Damages $405,671.00<br />

3. Additional Cost <strong>of</strong> Undercutting $ 13,571.25<br />

4. Rideability Incentive -0-<br />

5. Rehandling <strong>of</strong> Stockpiled Materials -0-<br />

6. Attorney’s Fees and Costs -0-<br />

TOTAL DAMAGES $590.883.06<br />

Plus Pre-judgment Interest (28.67%) + $169,406.17<br />

TOTAL $760,289.23<br />

112