construction problems that arise. However, the Department does not assume<br />

responsibility for the work as a consequence <strong>of</strong> such cooperation.<br />

(Ex. P-60 at p. 102-2).<br />

206. Section 102.05 <strong>of</strong> the 408 Specifications states:<br />

Time estimates for the placement, replacement, relocation, adjustment and reconstruction<br />

<strong>of</strong> public and private facilities and structures on, under, or over the project and waste and<br />

borrow areas not on the project before and during the performance <strong>of</strong> the work have been<br />

provided only for informational purposes. The Department does not warrant the accuracy<br />

<strong>of</strong> the time estimates. Bidders should verify this information by contacting the owners <strong>of</strong><br />

the facilities and structures. These time estimates are not to be considered part <strong>of</strong> the bid<br />

proposal.<br />

(Ex. P-60 at p. 102-5).<br />

207. Paragraph 6 <strong>of</strong> the Contract states:<br />

The contractor further covenants that he has not relied upon any information provided by<br />

the Department, including information contained in the Special Provisions, concerning<br />

the time within which publicly or privately-owned facilities below, at or above the<br />

ground are expected to be installed, removed, repaired, replaced, and/or relocated; that he<br />

has not relied upon any information provided by the Department concerning the location<br />

or existence <strong>of</strong> all such facilities that might be below, at or above ground; that he has<br />

contacted or will contact all owners <strong>of</strong> such facilities to verify the location and position <strong>of</strong><br />

all such facilities and the time within which work on such facilities will be performed;<br />

and that he is aware delays might be incurred in the performance <strong>of</strong> work on this project<br />

as a result <strong>of</strong> work being performed or that will be performed on such facilities by their<br />

owners.<br />

It is further understood that, notwithstanding assistance <strong>of</strong> any kind and extent that might<br />

be provided by the department, the contractor, in every instance, bears the ultimate<br />

responsibility in resolving all disputes <strong>of</strong> every kind with the owners <strong>of</strong> such facilities.<br />

The contractor agrees to save and hold the Department harmless from liability for all<br />

delays, interference and interruptions that might arise during the performance <strong>of</strong> the work<br />

on this project as a result <strong>of</strong> work being or that will be performed on such publicly or<br />

privately-owned facilities.<br />

(Ex. P-8 at p. 5).<br />

208. The “Utilities” provision <strong>of</strong> the Contract also provided that the contractor had the<br />

following duties regarding the relocation:<br />

Cooperate with the public utility companies and local authorities in the placement,<br />

replacement, relocation, adjustment or reconstruction <strong>of</strong> their structures and<br />

facilities during construction.<br />

27