12.04.2015 Views

3720 - Board of Claims

3720 - Board of Claims

3720 - Board of Claims

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

PennDOT’s failure to address the guy wire/design problem from the start <strong>of</strong> construction<br />

(August 2001) until the end <strong>of</strong> March 2002.<br />

Inadequate Assistance with Pole Relocation<br />

With respect to PennDOT’s exceedingly slow and inadequate response to Intercounty’s<br />

request for help with the pole relocation problems during the first six months <strong>of</strong> construction, we<br />

start with Mr. Pilosi’s initial representations at the June 11 pre-job meeting. At this meeting,<br />

Mr. Pilosi, as PennDOT’s District 4-0 Utilities Administrator, stated that PennDOT and he<br />

would coordinate and address utility pole relocation issues going forward. However, his abject<br />

failure to do so for the first six months <strong>of</strong> the Project, despite repeated requests by Intercounty<br />

for assistance in expediting this work, was, in our view, a material and contributing cause <strong>of</strong> the<br />

overall delay and disruption to the Project.<br />

To understand the impact <strong>of</strong> PennDOT’s actions/inaction here, we note first that<br />

Mr. Sebastianelli, PennDOT’s inspector-in-charge for the Project, was on site daily and was well<br />

aware <strong>of</strong> the problems created for Intercounty by the initial seven week starting delay and the<br />

slower than expected pace <strong>of</strong> the pole relocation. 14<br />

He was also aware early on (or should have<br />

been aware at least by mid-October 2001 when the Utilities left the job without even starting in<br />

Section Two or One) that any further delay in the planned relocation <strong>of</strong> the poles and wires<br />

would so disrupt Intercounty’s work schedule (as dictated by PennDOT's Construction<br />

Sequence) that unless prompt action to correct this problem was taken, Intercounty’s work could<br />

not be completed as planned. Mr. Sebastianelli also knew during this early period <strong>of</strong> the Project,<br />

July through December 2001, that all pole relocations for the Project should have been<br />

14 Mr. Sebastianelli, the PennDOT employee with the most first-hand knowledge about the Project's daily progress<br />

and delays, was not called by PennDOT to testify at trial. As a result, the testimony <strong>of</strong> Mr. Nansteel regarding the<br />

Project’s progress, the utility pole relocation delay problems and discussions with PennDOT personnel on site stands<br />

largely uncontradicted.<br />

78

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!