12.04.2015 Views

3720 - Board of Claims

3720 - Board of Claims

3720 - Board of Claims

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

71. Because the Contract (including the 408 Specifications) contained no warranty that<br />

unsuitable material would not be encountered in the subgrade, and no representations regarding the<br />

quantity <strong>of</strong> unsuitable material it would be required to excavate and replace due to instability in<br />

this subgrade, but, in fact, contemplated the possibility <strong>of</strong> such work and provided for a unit<br />

method <strong>of</strong> payment for same based on the classification <strong>of</strong> such excavation; and because<br />

Intercounty failed to establish the extent <strong>of</strong> the unsuitable material encountered on the Project was<br />

so excessive in volume or so unusual in nature as to constitute a differing site condition;<br />

Intercounty is not entitled to recover additional compensation for this work over and above the<br />

specified bid rate on grounds that this work or the amount <strong>of</strong> undercut constituted an undisclosed<br />

or differing site condition pursuant to Section 110.02 <strong>of</strong> the 408 Specifications. Ex. P-8; 408<br />

Specifications §§ 110.02, 203, 210.3, 210.4; Angelo Iafrate Construction Co., Inc. v. Pennsylvania<br />

Tpk. Commission, No. 3654, 2006 WL 2585020 at *50-52 (Pa. Bd. <strong>Claims</strong>, July 27, 2006).<br />

72. Class 1 Excavation is defined by Section 203.1(a) <strong>of</strong> the 408 Specifications as, inter<br />

alia, “[e}xcavation, as indicated or directed, for the removal <strong>of</strong> unsuitable material having a bottom<br />

width <strong>of</strong> 2.5 m (8 feet) or more.” 408 Specifications § 203.1(a).<br />

73. The bulk <strong>of</strong> the excavation <strong>of</strong> unsuitable material in the subgrade on the Project (i.e.<br />

the “undercut”) was Class 1 Excavation and was properly paid for by PennDOT at the bid rate <strong>of</strong><br />

$9 per cubic yard. Ex. P-5, P-8; 408 Specifications § 203.<br />

74. However, because 470 cubic yards <strong>of</strong> the “undercut” had a bottom width <strong>of</strong> less<br />

than 8 feet, it is most appropriately defined as Class 1A Excavation under Section 203.1(b) <strong>of</strong> the<br />

408 Specifications and constitutes “extra work” that is defined by Section 110.03(c) <strong>of</strong> the 408<br />

Specifications as “work having no quantity and/or price included in the contract, which is<br />

determined by the District Engineer to be necessary and desirable to complete the Project.” Ex. P-<br />

8; 408 Specifications §§ 110.03(c), 203.1(b).<br />

75. Because Intercounty adequately established that its actual cost for undercuts <strong>of</strong> less<br />

than 8 feet bottom width was fairly estimated at $34 per cubic yard, and because Intercounty has<br />

already been paid $4,230 for this work, Intercounty is entitled to be paid an additional $11,750 for<br />

the undercutting performed on the Project. 408 Specifications §§ 110.03(c), 203.1(b).<br />

76. With appropriate markup, PennDOT is liable for $13,571.25 as a further payment to<br />

Intercounty for undercut work outside the Class 1 Excavation category performed on the Project.<br />

Ex. P-5, P-8; 408 Specifications §§ 110.03(c), 203.<br />

77. Although Intercounty makes a claim for additional disruption damages for the<br />

undercut due to the extra movement <strong>of</strong> men and equipment up and down the roadway because the<br />

Project had to be worked in a non-linear sequence, we cannot estimate the additional cost <strong>of</strong> this<br />

undercutting work with any reasonable degree <strong>of</strong> certainty because Intercounty has failed to<br />

provide us with a calculation, methodology or evidence from which to calculate this particular loss<br />

<strong>of</strong> productivity. Spang & Co. v. U.S. Steel Corp., 545 A.2d at 866-867; Angelo Iafrate<br />

Construction Co., Inc. v. Pennsylvania Tpk. Commission, No. 3654, 2006 WL 2585020 at *59-63<br />

(Pa. Bd. <strong>Claims</strong>, July 27, 2006).<br />

59

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!