3720 - Board of Claims
3720 - Board of Claims
3720 - Board of Claims
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
8. To minimize erosion, the Conservation District required PennDOT to submit for<br />
approval an Erosion and Sediment Pollution Control Plan ("E and S Plan"). This plan specified a<br />
detailed sequence <strong>of</strong> how the Project would be built with the contractor working in only one<br />
section, or one-third <strong>of</strong> the Project, at a time. N.T. 12, 133, 225, 1071-1072; Exs. P-8, P- 59.<br />
9. The Conservation District approved PennDOT’s E and S Plan and PennDOT then<br />
incorporated it into the Contract’s plans and drawings. PennDOT also put it in the Special<br />
Provisions <strong>of</strong> the Contract and renamed it the “Construction Sequence.” Thus, PennDOT made<br />
the E and S Plan into the roadway Construction Sequence and incorporated this unusually specific<br />
plan <strong>of</strong> construction activities into the Contract for the Project. N.T. 444-445, 1071-1072; Exs. P-<br />
59, P-2A, P-2B, P-8.<br />
10. PennDOT included the Construction Sequence in the bid and Contract documents.<br />
Accordingly, the Construction Sequence was to be used by the successful bidding contractor to<br />
price and perform the work. Exs. P-2A, P-2B; Philadelphia Warehousing and Cold Storage v.<br />
Hallowell, 490 A.2d 955, 956-57 (Pa. Cmwlth. 1985); American Totalisator Co., Inc. v. Seligiman,<br />
384 A.2d 242, 258 (Pa. Cmwlth. 1977); see also, Durkee Lumber Co., Inc. v. Dep’t <strong>of</strong><br />
Conservation and Natural Res., No. 3797, 2008 WL 509459 at *26-27 (Pa. Bd. <strong>Claims</strong>, Jan. 4,<br />
2008), citing Ezy Parks v. Larson, 454 A.2d 928, 933 (Pa. 1982).<br />
11. The Contract required that, pursuant to the Construction Sequence, work on the<br />
Project would be performed in specified sections and phases while the roadway remained open to<br />
traffic. The roadway was divided into three roughly equal sections (Sections One, Two and Three)<br />
and within each section there were three phases <strong>of</strong> work (comprised <strong>of</strong> multiple steps) to be<br />
accomplished. N.T. 153; Exs. P-2A, P-8.<br />
12. Pennsylvania utility companies have the privilege <strong>of</strong> free occupancy <strong>of</strong> PennDOT’s<br />
public rights-<strong>of</strong>-way for the installation <strong>of</strong> their poles, wires and other facilities. In return, when<br />
PennDOT alters a state highway, these utility companies owe a corresponding duty to PennDOT to<br />
relocate their poles, wires and other facilities at their own cost at the time, and to the location<br />
within such rights-<strong>of</strong>-way, as PennDOT determines. 36 P.S. Sec. 670-411, 67 Pa. Code Sec.<br />
459.1; Exs. P-38, P-35; see Delaware River Port Authority v. P.U.C., 145 A.2d 17 (1958);<br />
Department <strong>of</strong> Transportation v. Pennsylvania Power & Light Co., 383 A.2d 1314, 1317-1318 (Pa.<br />
Cmwlth. 1978).<br />
13. The Contract (in Paragraph 6, in the “Utilities” section <strong>of</strong> the Special Provisions,<br />
and in the 408 Specifications Sections 105.06(b), 105.06(a) and 102.05) imposed certain duties on<br />
Intercounty to contact and cooperate with the affected utility companies in connection with the<br />
utility pole and wire relocation work on the Project. Ex. P-8; Pub. 408 Specifications §§ 102.05,<br />
105.06(a) and 105.06(b).<br />
14. However, Intercounty’s duties to contact and cooperate with the affected utility<br />
companies in connection with the utility pole and wire relocation on the Project commenced only<br />
upon completed execution <strong>of</strong> the Contract by both Intercounty and PennDOT. Ex. P-8; 408<br />
Specifications §§ 103.03, 103.05(b), 103.07.<br />
47