12.04.2015 Views

3720 - Board of Claims

3720 - Board of Claims

3720 - Board of Claims

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

mid-October 2001 (when the Utilities left the Project without touching Sections Two and One) to<br />

January 2002, despite his representations at the June 11 meeting, remains without reasonable<br />

explanation. 19<br />

Applying the case law established by Pennsylvania's courts in Coatesville, General<br />

Asphalt and their progeny to the case at bar, the <strong>Board</strong> finds that the representations <strong>of</strong> PennDOT<br />

personnel that they were working to coordinate and expedite the utility pole relocation from the<br />

outset <strong>of</strong> work on the Project when, in fact, they were not, constituted active interference with<br />

Intercounty’s work on the Project. See also, Department <strong>of</strong> General Services v. Pittsburgh<br />

Building Co., 920 A.2d 973, 991 (Pa. Cmwlth. 2007) (The Court found that DGS's actions in<br />

withholding a memo about adverse soil conditions and directing the contractor to commence<br />

work in contradiction <strong>of</strong> same deceived the contractor and actively interfered with its work).<br />

James Corp. v. North Allegheny School District, 938 A.2d 474 (Cmwlth. Ct. 2007) (The Court<br />

found active interference and misrepresentation by the school district that first told the contractor<br />

that the E & S permit had been issued pre-bid when it had not); See also, S.J. Groves & Sons,<br />

Co., 343 A.2d at 72; Gasparini, 187 A.2d at 162.<br />

PennDOT's affirmative misrepresentations with regard to the role it would undertake<br />

post-Contract in utility pole relocations in this case are ample grounds for dismissal <strong>of</strong> the<br />

several exculpatory provisions relied upon by PennDOT to relieve it from responsibility for the<br />

delay and disruption caused to Intercounty. However, there are several other circumstances here<br />

which we also find to constitute active interference with Intercounty's work by PennDOT. The<br />

most significant <strong>of</strong> these additional circumstances are PennDOT’s initial failure to include<br />

19 If, indeed, it was not Mr. Pilosi’s job to communicate with the Utilities on pole relocation problems once the<br />

Project commenced, why did he represent that he would do so at the June 11, 2001 pre-job meeting and why did Mr.<br />

Sebastianelli perpetuate this representation by his conduct for the first six months <strong>of</strong> the Project?<br />

90

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!