12.04.2015 Views

3720 - Board of Claims

3720 - Board of Claims

3720 - Board of Claims

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

so poles around Section Two, the inability to place these poles would have prevented the transfer<br />

or restringing <strong>of</strong> the utility wires in the affected section(s). This, in turn, precluded removal <strong>of</strong><br />

the old poles (the actual physical impediment to the new road work) until final resolution <strong>of</strong> all<br />

the guy wire pole placement problems. Thus, it is no surprise that the Utilities, concerned with<br />

minimizing their time on the job and maximizing their pole relocation efforts, left the job site in<br />

October 2001 after completion <strong>of</strong> Section Three, and did not return until March 25, 2002 to<br />

resume work in Section Two after the guy wire/design problem in Section Two was finally<br />

resolved. Thus, we believe that the seven month delay in resolving the “guy wire issue” had a<br />

major, adverse impact on the utility pole relocation efforts on the Project and, was, in turn, the<br />

fundamental cause <strong>of</strong> the 223 day delay and the ongoing disruption to Intercounty’s work on the<br />

Project.<br />

III. LIABILITY<br />

As set forth above, we have found that Intercounty suffered 223 days <strong>of</strong> delay and<br />

ongoing disruption to its work on the Project because PennDOT hindered its work and actively<br />

interfered with its performance <strong>of</strong> the Contract in the following ways: 1) by failing to act in a<br />

manner necessary to prosecution <strong>of</strong> the work by its failure to adequately coordinate the utility<br />

pole relocations into its plan for the roadway in the pre-Contract design phase and its failure to<br />

provide Intercounty with plans and drawings adequate to build the Project; (2) by representing to<br />

Intercounty that it would coordinate utility pole relocation and address any problems with the<br />

Utilities once the work started, when, in fact, it did nothing to address pole relocation problems<br />

for the first six months <strong>of</strong> the Project; (3) by ordering Intercounty to work the Project in a<br />

substantially different sequence than set forth in the bid documents causing disruption and<br />

inefficiencies rather than suspending work when the utility pole relocation delays meant the<br />

86

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!