Mr. Pilosi to address these problems. Neither Mr. Sebastianelli, Mr. Pilosi nor anyone else from<br />

PennDOT ever responded to these requests for assistance by telling Intercounty personnel that<br />

they should be contacting the Utilities directly about pole relocation arrangements or problems<br />

during the Project.<br />

On June 18, 2001 (one week after the pre-job meeting), PennDOT issued its Notice to<br />

Proceed. The contract completion date was therefore scheduled to be November 6, 2002.<br />

True to its word, Intercounty adapted its work plan to the flipped sequence and started<br />

work in Section Three promptly by doing the surveying and staking work necessary for the pole<br />

relocations to commence. Intercounty completed the right-<strong>of</strong>-way stakeout work in Section<br />

Three by July 1, 2001 (slightly more than two weeks from the pre-job meeting). Intercounty<br />

then immediately proceeded to do the same surveying and staking work in Section Two and in<br />

Section One, completing both <strong>of</strong> those sections by August 1, 2001. This provided the<br />

opportunity to relocate poles through all three sections <strong>of</strong> the Project without stopping from<br />

August 1, 2001 onward.<br />

Intercounty reasonably expected pole relocation to begin on or about July 2, 2001 after<br />

surveying and staking were completed in Section Three, and to continue relatively uninterrupted<br />

through Section Two and Section One, taking approximately one month in each section and<br />

concluding in early October 2001 based on the bid documents (including Construction Sequence<br />

and “Utilities” section <strong>of</strong> the Contract). However, the actual pole relocation was vastly different.<br />

Specifically, actual pole relocation did not begin on site until August 21, 2001 (seven weeks late)<br />

and did not complete in Section Three until October 14, 2001 (several days after all pole<br />

relocations for the Project were expected to be complete). At this point, the Utilities left the site<br />

and did not return to proceed with utility pole relocation until late March <strong>of</strong> 2002, a hiatus <strong>of</strong><br />

74