y Chad Nansteel (Project Superintendent) and Geinek Puc (Project Manager) due to delay.<br />

Although Intercounty <strong>of</strong>fered testimony that both men worked exclusively on the SR 2001<br />

Project from November 6, 2002 to June 17, 2003, the evidence presented establishes that only<br />

the last 2 months (i.e. from mid-April 2003 until mid-June 2003) were actually spent working on<br />

the job site, since Project work had been suspended for Winter and not resumed in 2003 until<br />

mid-April. Additionally, Intercounty's own job cost records show only $16,284.23 in<br />

supervisory costs attributable to the SR 2001 Project in 2003, not the full $89,731.00 claimed.<br />

Given the winter work suspension, we find that the job cost report amount <strong>of</strong> $16,284.23 most<br />

accurately reflects the actual supervisory cost incurred by Intercounty during the extended period<br />

for the SR 2001 Project. However, because we have applied the markups prescribed by Sections<br />

110.03(d)(4) and (7) to Intercounty's other costs (as per its request); and because these markups<br />

are intended to compensate Intercounty for the cost <strong>of</strong> general and project superintendence, we<br />

will not reimburse Intercounty twice for this activity and will decline to make a separate award<br />

for Extended Project Supervision.<br />

In summation, the <strong>Board</strong> finds that Intercounty incurred a total <strong>of</strong> $171,640.81 in<br />

damages due to the delay caused by PennDOT's active interference with work on the Project.<br />

This amount is comprised <strong>of</strong>:<br />

$12,470.02 for Extended Field Conditions;<br />

$14,225.79 for Extended MPT; and<br />

$144,945.00 for Material Cost Escalation.<br />

Compensation for Extended Project Supervision is included in markups to the above three<br />

categories and will not be awarded separately.<br />