3720 - Board of Claims
3720 - Board of Claims
3720 - Board of Claims
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
II. UTILITY POLE RELOCATION ISSUES<br />
Pre-Contract Activity<br />
As with all significant construction projects, PennDOT road rehabilitation and widening<br />
projects are typically preceded by extensive design work and planning well before any actual<br />
construction work begins. In fact, much <strong>of</strong> the necessary design and planning, including plan<br />
approvals and permitting, occurs before the project is put out for bid or any contracts are<br />
awarded. One <strong>of</strong> these critical pre-construction activities on a roadway reconstruction/widening<br />
project, such as the one here at issue, is to plan for utility pole relocation, as needed, to build the<br />
project on time and as designed. To accomplish this, PennDOT has created within its Bureau <strong>of</strong><br />
Design a Utility Relocation Unit. This Unit operates on a more local level through district<br />
Utilities Relocation Administrators. The district utility relocation units are comprised <strong>of</strong> one or<br />
more PennDOT employees whose job is to plan ahead and make appropriate arrangements with<br />
utility companies about moving their poles and facilities so that road construction projects can be<br />
completed on time.<br />
In the present case, three utility companies (also referred to herein as the "Utilities") had<br />
poles and wires in the construction area <strong>of</strong> the SR 2001 Project. During the approximate two<br />
year period before actual work on the Project site began, the Utility Relocation Administrator for<br />
District 4-0 sent each local utility company a preliminary set <strong>of</strong> PennDOT's plans and drawings<br />
for the Project identifying which utility facilities would have to be relocated. In return,<br />
PennDOT received from each utility company a list <strong>of</strong> new poles to replace those needed to be<br />
moved, along with work time estimates to relocate these poles.<br />
In approximately<br />
November/December 1999, the telephone utility, G.T.E. <strong>of</strong> Pennsylvania ("G.T.E."), notified<br />
PennDOT it would need sixty days to relocate its wires and poles for the Project. The electric<br />
67