12.04.2015 Views

3720 - Board of Claims

3720 - Board of Claims

3720 - Board of Claims

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

approximately five months. Actual pole relocation in Section Two and Section One eventually<br />

occurred from on or about March 25, 2002 to July 25, 2002. Complete utility pole relocation, in<br />

addition to progressing in fits and starts not at all close to the coordinated work set forth in the<br />

Construction Sequence and “Utilities” section <strong>of</strong> the Contract, did not conclude until nearly 300<br />

days later than reasonably anticipated by Intercounty.<br />

This exceedingly long delay in pole relocation, together with the start and stop progress<br />

<strong>of</strong> same, in turn, clearly delayed and disrupted Intercounty’s work throughout the length <strong>of</strong> the<br />

Project and was the cause <strong>of</strong> the Project ultimately being completed 223 days late. Specifically,<br />

the late start and slow progress <strong>of</strong> the utility pole relocation initially hindered Intercounty’s<br />

progress on the Project by causing it to run out <strong>of</strong> planned work while it performed less<br />

productive tasks and waited for poles to be moved. This was particularly evident in the Fall <strong>of</strong><br />

2001, as Intercounty’s work was then confined to Section Three by the Construction Sequence<br />

and the E & S Plan. This initial problem then became worse in November 2001. Following the<br />

Utilities’ departure from the job site and an oral request by Intercounty to demobilize in late<br />

October 2001 due to the pole relocation delay, which request was flatly rejected,<br />

Mr. Sebastianelli, in early November 2001, notified Intercounty that he would hold weekly<br />

“partnering meetings.” At these “partnering meetings” Mr. Sebastianelli changed the scheduled<br />

work plan in order to insure that Intercounty could keep working around the obstructing poles.<br />

At these meetings, which continued throughout the remainder <strong>of</strong> the Project, Mr. Sebastianelli<br />

cast aside the Construction Sequence and each week created an ad hoc list <strong>of</strong> tasks for<br />

Intercounty to perform. These new work lists were called either “Schedule <strong>of</strong> Operations” or<br />

"Weekly Schedule", and from November 2001 through the end <strong>of</strong> the Project they replaced the<br />

original Construction Sequence and dictated where and in what order Intercounty had to perform<br />

75

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!