12.04.2015 Views

3720 - Board of Claims

3720 - Board of Claims

3720 - Board of Claims

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

adequate room for guy wires in its roadway design and its subsequent failure to resolve this<br />

problem in a timely manner.<br />

PennDOT had a duty to properly plan and design the Project. U. S. v. Spearin, 248 132,<br />

39 S.Ct. 59 (1918); Canuso v. City <strong>of</strong> Philadelphia, 192 A. 133, 136 (Pa. 1937); Department <strong>of</strong><br />

Transportation v. W.P. Dickerson & Son, Inc., 400 A.2d 930, 932 (Pa. Cmwlth. 1979);<br />

Allentown Supply Corp. v. Stryer, 195 A.2d 274, 299 (Pa. Super. 1963); Angelo Iafrate<br />

Construction Co., Inc. v. Pennsylvania Turnpike Commission, No. 3654, 2006 WL 2585020 at<br />

*29-30, 41-42 (Pa. Bd. <strong>Claims</strong>, July 27, 2006) (affirmed by Commonwealth Court in unreported<br />

opinion). However, the evidence establishes that PennDOT’s design did not allow sufficient<br />

room for guy wires in the right-<strong>of</strong>-way at several new pole locations (which locations PennDOT<br />

itself had authorized). In August 2001, early in the Project, the Utilities notified PennDOT that<br />

they could not move certain poles around these locations because the poles were supported by<br />

guy wires and there was no room for the wires at the newly designated pole locations. It then<br />

took seven months for PennDOT to correct this design and planning mistake by redesigning the<br />

roadway in order to get those poles moved in so the guy wires fit in the right-<strong>of</strong>-way. Section<br />

107.18 <strong>of</strong> the 408 Specifications, entitled “Furnishing Right <strong>of</strong> Way,” states that ‘[t]he<br />

Department will be responsible for securing all necessary rights-<strong>of</strong>-way in advance <strong>of</strong><br />

construction.” (Ex. P-60). By not planning enough room for these guy wires, PennDOT failed to<br />

fulfill its responsibility to coordinate with the Utilities in the pre-Contract design phase and also<br />

failed to provide Intercounty with plans and drawings adequate to build the Project as designed.<br />

Delays in construction occasioned by the necessity <strong>of</strong> altering plans because <strong>of</strong><br />

PennDOT’s failure to originally provide an adequate design are properly charged to PennDOT.<br />

C. J. Langenfelder & Son, Inc. v. Department <strong>of</strong> Transportation, 404 A.2d 745, 750-751<br />

91

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!