12.04.2015 Views

3720 - Board of Claims

3720 - Board of Claims

3720 - Board of Claims

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

in" or creating embankments along the roadway as needed. The Contract bid documents<br />

(including plans and drawings) indicated that this activity would entail digging approximately<br />

50,000 cubic yards <strong>of</strong> material, primarily out <strong>of</strong> Section Three, with about half <strong>of</strong> that (25,000<br />

cubic yards) being used to build the embankments in Section One and Section Two, with the rest<br />

being wasted. (Ex. P-8 at p. 8; N.T. 625). At the beginning <strong>of</strong> the Project, when Intercounty<br />

started in Section Three, it carved the excess material from the hillside as the plans required, then<br />

placed that material in a stockpile. Months later, Intercounty hauled the material to Section One,<br />

and then Section Two, and created the required embankments. Intercounty claims that its costs<br />

for stockpiling and re-handling the material were not covered by the Contract and/or were caused<br />

by the "flipped" Construction Schedule (i.e. the decision at the pre-job meeting <strong>of</strong> June 11, 2001<br />

to start in Section Three instead <strong>of</strong> Section One). Intercounty therefore reasons that it should be<br />

paid for the extra costs entailed in re-handling the fill material.<br />

To begin with, the Contract provides that the roadway work <strong>of</strong> excavating hillside and<br />

building embankment was Class 1 Excavation. (Exs. P-8 at p. 8, P-60 at p. 203-1). The 408<br />

Specifications provide that the payment allotted in the Contract for the Class 1 Excavation<br />

includes the building <strong>of</strong> the embankments and that no extra payment will be made for hauling<br />

material, wasting material or purchasing borrow material for replacement. 23<br />

Additionally, the<br />

Contract’s original Construction Sequence included in the bid documents provided that the<br />

contractor could only work in one section at a time, so wherever Intercounty started to work, it<br />

23 Under Section 203.3(j) <strong>of</strong> the 408 Specifications, payment for Class 1 Excavation includes hauling excavated<br />

material that is suitable for embankment construction for placement in embankments and in backfills. In Section<br />

206.4 (a), the Specifications also provide that embankment construction is considered incidental to the excavation<br />

items from which the embankment material is obtained and will not be paid separately. Id. Sections 205.3(a) and<br />

205.4(a) <strong>of</strong> the Specifications provide that embankment material is to come from the classes <strong>of</strong> excavation on the<br />

project, that if the contractor wastes material suitable for embankment construction it must replace it with an<br />

equivalent volume <strong>of</strong> suitable material and further that, while the contractor may, for its convenience, waste<br />

excavated material that is suitable for embankment construction and replace it with “borrow material” (obtained<br />

from sources other than this project's excavations), the contractor will not be paid for the replacement material. (Ex.<br />

P-60; Exs. D-7, D-8, D-9).<br />

104

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!