3720 - Board of Claims
3720 - Board of Claims
3720 - Board of Claims
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
its Contract work. (Exs. P-20, P-21, P-25, P-31, P-36, P-40, P-41, P-42, P-44, P-46, P-50).<br />
PennDOT's wholesale abandonment <strong>of</strong> the linear Construction Sequence originally anticipated<br />
by Intercounty was further expanded in early 2002 when PennDOT was able to persuade the<br />
Pike County Conservation District to approve a revised E & S Plan that would allow Intercounty<br />
to work in more than one section at a time.<br />
PennDOT's decision to abandon the Construction Schedule and jockey Intercounty's<br />
work locations around the Project site on a weekly basis, in lieu <strong>of</strong> demobilizing until the utility<br />
poles could be moved, forced Intercounty to work in an inefficient and disrupted manner<br />
throughout the end <strong>of</strong> 2001 and all <strong>of</strong> 2002 to try to meet the November 2002 Contract<br />
completion date. This disruption to its work became pervasive: causing Intercounty to move<br />
trucks and equipment in and around the existing poles, wires and utility equipment in<br />
prosecuting its work (including its cut and fill, grading, trenching, piping and sub-base<br />
operations) during all phases <strong>of</strong> road widening and reconstruction; requiring Intercounty to take<br />
steps to avoid interfering with the utility’s work crews when they did appear on the job; and<br />
requiring Intercounty to work and pave around utility poles when it was able to prosecute its<br />
work. Moreover, it had to do this work, as dictated by PennDOT, in multiple sections and on<br />
multiple phases simultaneously throughout 2002 in a more spread out manner then reasonably<br />
anticipated. From March 2002 to October 2002, Intercounty regularly had its crews working in<br />
either two or three sections at once, instead <strong>of</strong> in the more compact and linear progression<br />
dictated by the bid documents. For instance, in June 2002, Intercounty was strung out along the<br />
entire roadway, working in all three sections and using extra flagmen to divert traffic back and<br />
forth across the road while its crews and equipment excavated and paved around existing poles<br />
76