12.04.2015 Views

3720 - Board of Claims

3720 - Board of Claims

3720 - Board of Claims

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

its Contract work. (Exs. P-20, P-21, P-25, P-31, P-36, P-40, P-41, P-42, P-44, P-46, P-50).<br />

PennDOT's wholesale abandonment <strong>of</strong> the linear Construction Sequence originally anticipated<br />

by Intercounty was further expanded in early 2002 when PennDOT was able to persuade the<br />

Pike County Conservation District to approve a revised E & S Plan that would allow Intercounty<br />

to work in more than one section at a time.<br />

PennDOT's decision to abandon the Construction Schedule and jockey Intercounty's<br />

work locations around the Project site on a weekly basis, in lieu <strong>of</strong> demobilizing until the utility<br />

poles could be moved, forced Intercounty to work in an inefficient and disrupted manner<br />

throughout the end <strong>of</strong> 2001 and all <strong>of</strong> 2002 to try to meet the November 2002 Contract<br />

completion date. This disruption to its work became pervasive: causing Intercounty to move<br />

trucks and equipment in and around the existing poles, wires and utility equipment in<br />

prosecuting its work (including its cut and fill, grading, trenching, piping and sub-base<br />

operations) during all phases <strong>of</strong> road widening and reconstruction; requiring Intercounty to take<br />

steps to avoid interfering with the utility’s work crews when they did appear on the job; and<br />

requiring Intercounty to work and pave around utility poles when it was able to prosecute its<br />

work. Moreover, it had to do this work, as dictated by PennDOT, in multiple sections and on<br />

multiple phases simultaneously throughout 2002 in a more spread out manner then reasonably<br />

anticipated. From March 2002 to October 2002, Intercounty regularly had its crews working in<br />

either two or three sections at once, instead <strong>of</strong> in the more compact and linear progression<br />

dictated by the bid documents. For instance, in June 2002, Intercounty was strung out along the<br />

entire roadway, working in all three sections and using extra flagmen to divert traffic back and<br />

forth across the road while its crews and equipment excavated and paved around existing poles<br />

76

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!