26.03.2013 Views

Lost River - Karst Information Portal

Lost River - Karst Information Portal

Lost River - Karst Information Portal

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

2007 NSS Convention Guidebook<br />

continued toward the<br />

T, while the T team<br />

kept working. The<br />

third team worked in<br />

the areas adjacent to<br />

and in the Cushing<br />

Room. Richard Blenz<br />

Nature Conservancy<br />

President Anmar<br />

Mirza and others<br />

created a section of<br />

scaffolding in the<br />

Cushing Room,<br />

which was very<br />

useful. At the earliest<br />

stage of the project,<br />

all equipment and<br />

gear was stowed away<br />

securely, but as the<br />

project proceeded, approval was given by the eboard<br />

to leave the air, power, and phone lines set<br />

up inside the cave, which expedited equipment<br />

set up and stowage time needed for each project<br />

workday, which were held monthly.<br />

From May to November 2006, workdays<br />

were held on both Saturday and Sunday in order<br />

to maximize the time spent while equipment<br />

was set up and volunteers were available, and<br />

also in hopes of encouraging weekend-long<br />

activity by cavers who had to travel a long<br />

distance to participate. During the winter<br />

months, which typically hold less appeal for<br />

camping in Indiana, efforts were scaled back to<br />

a single workday per month, held on a Saturday.<br />

The work weekends resumed in March 2007,<br />

and plans are to continue that pattern into the<br />

summer months.<br />

It has been somewhat difficult for the<br />

Project Coordinator to be objective about the<br />

project results. At first it seemed to be going very<br />

slowly, and at times manpower was minimal.<br />

However, after looking at some photographs<br />

taken prior to much graffiti removal, it was a<br />

pleasant surprise to realize that a lot of graffiti<br />

had been removed in certain parts of the cave,<br />

which was very encouraging. Another big<br />

boost was to see one of the main walls of the<br />

Cushing Room come clean. It was formerly<br />

268<br />

The graffiti-covered wall after the work crews have passed.<br />

Photo by Brian Killingbeck.<br />

a particularly offensive area, and it was an<br />

extremely good feeling to see that change take<br />

place. It was absolutely astounding to imagine<br />

how in the world some of the offenders armed<br />

with spray paint were able to reach the spots<br />

they did in order to leave their mark. Even<br />

creating human pyramids doesn’t seem to be a<br />

plausible explanation for it. It’s a wonder that<br />

necks and other bones weren’t broken in order<br />

to leave certain graffiti.<br />

In the fall of 2006, the Project Coordinator<br />

got a verbal commitment from equipment<br />

manager Ray Keeler to continue to use the<br />

equipment beyond the initially-established<br />

one-year time frame, although it wasn’t<br />

discussed exactly how much longer. Once that<br />

commitment was made, efforts were started<br />

to open a hole large enough to permit air and<br />

power lines to be run into the cave through the<br />

former Domicile Pit entrance, which would<br />

allow graffiti removal in the Volcano Passage.<br />

That area is well beyond the reach of air lines<br />

where the compressor is currently set up at the<br />

main entrance. On the September 30 workday,<br />

a 5-inch diameter hole was dug 20 feet deep<br />

by Sam Frushour and Bill Baus, using hand<br />

augering equipment donated for use on that<br />

day by the Indiana Geological Survey. The hole<br />

was afterward protected with a length of PVC

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!