Project: 818550 Park Buildings - Rehabilitation<br />

Origination Year: 1996-97<br />

Planned Completion Year: Ongoing<br />

Department: Community Services<br />

Project Description / Scope / Purpose<br />

Project Information Sheet<br />

Type: Parks & Recreation<br />

Category: Infrastructure<br />

Project Manager: Bob Van Heusen<br />

Fund: 610 Infrastructure Renov & Replace<br />

Sub-Fund: 100 General Fund Assets<br />

Project Coordinator: Bob Van Heusen<br />

Park Buildings require renovations/upgrades for a multitude <strong>of</strong> reasons including code requirements, Americans with Disabilities Act (ADA) requirements, safety improvements, and/or repairs due<br />

to aging infrastructure. Park Buildings requiring improvements are identified by Facilities and Parks staff inspections. These projects are evaluated and prioritized according to applicable codes,<br />

safety issues, and other projects that might trigger work to the buildings, such as a playground renovation requiring ADA upgrades to bathrooms. Staff estimates the life span <strong>of</strong> remodel is 15 years.<br />

Funds in FY 2009/10 are for minor restroom upgrades, renovations at Lakewood Park snack shack, and design at Murphy Park. Murphy Park building renovation is scheduled for FY 2010/11 and<br />

will include energy efficient lighting, minor upgrades to HVAC, inspection and repair <strong>of</strong> concrete substrate flooring, inspection <strong>of</strong> doors, and kitchen fixtures, and replacement <strong>of</strong> windows and<br />

coverings. Funds in FY 2011/12 are for Serra and Fair Oaks satellite restrooms and FY 2012/13 funds are for nominal repairs at Washington Park, including painting, fixtures, multi-purpose room<br />

flooring and partitions, and bathrooms. Funds in FY 2013/14 are for renovations <strong>of</strong> Washington Park Pool building, restroom and concession restroom, as well the Raynor Park multi-purpose room<br />

and restrooms. Funds in FY 2014/15 are for upgrades to the bathrooms at Orchard Garden, Panama, and Fairwood parks. Funds in FY 2021/22 are for the upgrades at Serra Park; the renovation <strong>of</strong><br />

Ortega, Lakewood, and Ponderosa multi-purpose buildings; and the bathroom renovations at Ponderosa, Lakewood and Ortega Parks. Funds in FY 2022/23 are for the renovation/remodel <strong>of</strong> Braly<br />

Park and minor upgrades to Murphy Park multi-purpose buildings; minor repairs at Serra, Braly, and Murphy Park restrooms. FY 2023/24 and FY 2024/25 are for upgrades to snack shacks. Funds<br />

in FY 2025/26 are for HVAC replacement at Murphy Park.<br />

Project Evaluation and Analysis<br />

All Park buildings were included in a building assessment completed in 2000 when all components were evaluated and assigned replacement dates. Since then, Facilities staff has done numerous<br />

building assessments and have continued to upgrade Park buildings and components as needed. Recent ADA federal laws have required us to perform upgrades to buildings and building restrooms<br />

when other work such as playgrounds are refurbished. Regardless, we are required to have these upgrades in our plan whether or not other work occurs within the park. Additionally, many tiny-tot<br />

programs and other uses occur at Park buildings, making it a safety priority to complete these projects. Any delay in these projects may result in higher operational costs due to a higher frequency <strong>of</strong><br />

repairs and/or higher capital costs for emergency replacement.<br />

Fiscal Impact<br />

Staff estimates are based on costs from previous renovations and include program coordination and contingencies. Funding is from a transfer from the Park Dedication Fund. No additional<br />

operating costs are associated with these projects.<br />

Project Financial Summary<br />

Financial Data Prior<br />

Actual<br />

Project Costs<br />

Revenues<br />

Total<br />

Transfers-In<br />

Total<br />

Operating Costs<br />

Current 2010-11 2011-12 2012-13 2013-14 2014-15 2015-16 2016-17 2017-18 2018-19 2019-20 Y11-Y20<br />

2009-10<br />

Total<br />

Project<br />

Life Total<br />

1,452,446 173,296 308,000 485,000 222,643 227,204 173,804 0 0 0 0 0 819,389 3,861,782<br />

212,803 0 0 0 0 0 0 0 0 0 0 0<br />

0 212,803<br />

Park Dedication - Subdivisions 308,000 485,000 222,643 227,204 173,804 0 0 0 0 0 819,389<br />

283,228 173,375 308,000 485,000 222,643 227,204 173,804 0 0 0 0 0 819,389 2,692,643<br />

0 0 0 0 0 0 0 0 0 0 0 0<br />

0 0<br />

Park Buildings - Rehabilitation 818550