capacity <strong>of</strong> 1000 MW (4X250MW). CEA has<br />
cleared the Revised Cost Estimate amounting to<br />
Rs. 6621.32 Cr. at March ,03 PL including IDC &<br />
FC <strong>of</strong> Rs. 560 Cr. The CCEA approval to the<br />
Revised Cost Estimate is under process.<br />
STATUS OF THE PROJECT WORKS<br />
The work on Tehri Stage-l is in advance stage <strong>of</strong><br />
completion. The present status <strong>of</strong> the Project is<br />
as under:<br />
i) Dam<br />
The 260.5 m. high Earth & Rock Fill Dam,<br />
which would be the highest Earth &Rockfill<br />
Dam in the Asian Region and 4th highest in<br />
the world is in progress. Out <strong>of</strong> the total<br />
quantity <strong>of</strong> 256.67 Lac Cum, a quantity <strong>of</strong><br />
234.76 Lac. Cum. has been placed till<br />
March’04. The Dam has been raised to an<br />
average level <strong>of</strong> EL.838.30 m. Balance height<br />
left to be raised is only 1.20 m.<br />
ii) Spillways<br />
The works at various fronts viz., Chute<br />
Spillway, Right Bank Shaft Spillways and<br />
Left Bank Shaft Spillways is progressing well.<br />
The Open excavation for the entire spillways<br />
has been completed. The concreting <strong>of</strong><br />
‘Approach Channel, Control Structure &<br />
Spillway Chute has been completed. The<br />
underground excavation <strong>of</strong> ILO, Gate Shaft<br />
<strong>of</strong> lLO, T-1 & T-2 Shafts, Drainage Galleries<br />
around Stilling Basin has also been<br />
completed. The completion <strong>of</strong> ILO circuit viz.,<br />
ILO, Gate Shaft, Shaft & Tunnel T-3, Stilling<br />
basin required for commissioning <strong>of</strong> 1st unit<br />
is in advance stage <strong>of</strong> completion.<br />
The supply <strong>of</strong> Embedded parts <strong>of</strong> ILO Gates<br />
and Liners have been completed and erection<br />
is in advance stage <strong>of</strong> completion.<br />
iii) <strong>Power</strong> House<br />
a. Civil Works<br />
The Civil Works <strong>of</strong> <strong>Power</strong> House Complex<br />
have been completed except minor finishing<br />
works. All works <strong>of</strong> Intake Structure have<br />
been completed. Erection <strong>of</strong> steel liner and<br />
concreting in Lower Horizontal, vertical and<br />
lower bends <strong>of</strong> all the four vertical penstocks<br />
have been completed. The concrete lining in<br />
Tail Race Tunnels have also been<br />
completed.<br />
b) Supplies <strong>of</strong> E&M Equipment<br />
Supplies <strong>of</strong> generating plant and<br />
equipment from Russia/Ukraine, with<br />
financing arrangements by way <strong>of</strong><br />
Suppliers Credit, are complete.<br />
Computerised Control System supplies<br />
from ABB, Germany, with financing<br />
arrangements by way <strong>of</strong> Buyers Credit<br />
from KfW, Germany, have also been<br />
completed.<br />
All the 4 Nos., 306 MVA Generator<br />
Transformers, manufactured by M/s<br />
BHEL, have been transported & placed<br />
in the Transformer Bay.<br />
The Supplies under ICB for 420 KV Gas<br />
Insulated Switchgear and Busduct,<br />
awarded to Siemens, Germany, with<br />
financing under Buyers Credit from KfW,<br />
Germany are complete. c) Erection <strong>of</strong> E&M<br />
Equipment Assembly / Erection <strong>of</strong> <strong>Power</strong><br />
House Generating Plant and Equipment is<br />
in progress. Assembly <strong>of</strong> Generator<br />
Transformer accessories for unit-IV has been<br />
completed and is in progress for balance<br />
three units.<br />
Unit-IV<br />
Boxing <strong>of</strong> unit has been completed.<br />
Erection <strong>of</strong> Unit Auxiliaries & Station<br />
Auxiliaries have been completed.<br />
Pre-Commissioning Tests is almost<br />
complete.<br />
Unit-III<br />
The Erection <strong>of</strong> Spiral Casing, Pit Liner<br />
and concreting <strong>of</strong> Generator Barrel Floor<br />
upto EL. 605 m. has been completed.<br />
Erection <strong>of</strong> Turbine Operating Mechanism<br />
has been completed.<br />
The Stator has been lowered in the Pit<br />
and Winding/HV test has been completed.<br />
Rotor has been lowered in the pit and<br />
Erection <strong>of</strong> upper bracket completed. Final<br />
unit alignment is in progress.<br />
Boxing <strong>of</strong> unit is in advance stage <strong>of</strong><br />
completion.<br />
Unit-II<br />
Erection <strong>of</strong> Spiral Casing, Hydraulic Testing<br />
and concreting <strong>of</strong> Generator Barrel Floor<br />
upto EL. 605 M. has been completed.<br />
Erection <strong>of</strong> Turbine Operating Mechanism<br />
is in advance stage <strong>of</strong> completion.<br />
Stator Core Assembly in Service Bay is<br />
in progress.<br />
Rotor Assembly in Service Bay is in<br />
progress.<br />
Unit-I<br />
Erection <strong>of</strong> Draft Tube Cone, Stay Ring<br />
and Spiral casing has been completed.