100<br />

capacity <strong>of</strong> 1000 MW (4X250MW). CEA has<br />

cleared the Revised Cost Estimate amounting to<br />

Rs. 6621.32 Cr. at March ,03 PL including IDC &<br />

FC <strong>of</strong> Rs. 560 Cr. The CCEA approval to the<br />

Revised Cost Estimate is under process.<br />

STATUS OF THE PROJECT WORKS<br />

The work on Tehri Stage-l is in advance stage <strong>of</strong><br />

completion. The present status <strong>of</strong> the Project is<br />

as under:<br />

i) Dam<br />

The 260.5 m. high Earth & Rock Fill Dam,<br />

which would be the highest Earth &Rockfill<br />

Dam in the Asian Region and 4th highest in<br />

the world is in progress. Out <strong>of</strong> the total<br />

quantity <strong>of</strong> 256.67 Lac Cum, a quantity <strong>of</strong><br />

234.76 Lac. Cum. has been placed till<br />

March’04. The Dam has been raised to an<br />

average level <strong>of</strong> EL.838.30 m. Balance height<br />

left to be raised is only 1.20 m.<br />

ii) Spillways<br />

The works at various fronts viz., Chute<br />

Spillway, Right Bank Shaft Spillways and<br />

Left Bank Shaft Spillways is progressing well.<br />

The Open excavation for the entire spillways<br />

has been completed. The concreting <strong>of</strong><br />

‘Approach Channel, Control Structure &<br />

Spillway Chute has been completed. The<br />

underground excavation <strong>of</strong> ILO, Gate Shaft<br />

<strong>of</strong> lLO, T-1 & T-2 Shafts, Drainage Galleries<br />

around Stilling Basin has also been<br />

completed. The completion <strong>of</strong> ILO circuit viz.,<br />

ILO, Gate Shaft, Shaft & Tunnel T-3, Stilling<br />

basin required for commissioning <strong>of</strong> 1st unit<br />

is in advance stage <strong>of</strong> completion.<br />

The supply <strong>of</strong> Embedded parts <strong>of</strong> ILO Gates<br />

and Liners have been completed and erection<br />

is in advance stage <strong>of</strong> completion.<br />

iii) <strong>Power</strong> House<br />

a. Civil Works<br />

The Civil Works <strong>of</strong> <strong>Power</strong> House Complex<br />

have been completed except minor finishing<br />

works. All works <strong>of</strong> Intake Structure have<br />

been completed. Erection <strong>of</strong> steel liner and<br />

concreting in Lower Horizontal, vertical and<br />

lower bends <strong>of</strong> all the four vertical penstocks<br />

have been completed. The concrete lining in<br />

Tail Race Tunnels have also been<br />

completed.<br />

b) Supplies <strong>of</strong> E&M Equipment<br />

Supplies <strong>of</strong> generating plant and<br />

equipment from Russia/Ukraine, with<br />

financing arrangements by way <strong>of</strong><br />

Suppliers Credit, are complete.<br />

Computerised Control System supplies<br />

from ABB, Germany, with financing<br />

arrangements by way <strong>of</strong> Buyers Credit<br />

from KfW, Germany, have also been<br />

completed.<br />

All the 4 Nos., 306 MVA Generator<br />

Transformers, manufactured by M/s<br />

BHEL, have been transported & placed<br />

in the Transformer Bay.<br />

The Supplies under ICB for 420 KV Gas<br />

Insulated Switchgear and Busduct,<br />

awarded to Siemens, Germany, with<br />

financing under Buyers Credit from KfW,<br />

Germany are complete. c) Erection <strong>of</strong> E&M<br />

Equipment Assembly / Erection <strong>of</strong> <strong>Power</strong><br />

House Generating Plant and Equipment is<br />

in progress. Assembly <strong>of</strong> Generator<br />

Transformer accessories for unit-IV has been<br />

completed and is in progress for balance<br />

three units.<br />

Unit-IV<br />

Boxing <strong>of</strong> unit has been completed.<br />

Erection <strong>of</strong> Unit Auxiliaries & Station<br />

Auxiliaries have been completed.<br />

Pre-Commissioning Tests is almost<br />

complete.<br />

Unit-III<br />

The Erection <strong>of</strong> Spiral Casing, Pit Liner<br />

and concreting <strong>of</strong> Generator Barrel Floor<br />

upto EL. 605 m. has been completed.<br />

Erection <strong>of</strong> Turbine Operating Mechanism<br />

has been completed.<br />

The Stator has been lowered in the Pit<br />

and Winding/HV test has been completed.<br />

Rotor has been lowered in the pit and<br />

Erection <strong>of</strong> upper bracket completed. Final<br />

unit alignment is in progress.<br />

Boxing <strong>of</strong> unit is in advance stage <strong>of</strong><br />

completion.<br />

Unit-II<br />

Erection <strong>of</strong> Spiral Casing, Hydraulic Testing<br />

and concreting <strong>of</strong> Generator Barrel Floor<br />

upto EL. 605 M. has been completed.<br />

Erection <strong>of</strong> Turbine Operating Mechanism<br />

is in advance stage <strong>of</strong> completion.<br />

Stator Core Assembly in Service Bay is<br />

in progress.<br />

Rotor Assembly in Service Bay is in<br />

progress.<br />

Unit-I<br />

Erection <strong>of</strong> Draft Tube Cone, Stay Ring<br />

and Spiral casing has been completed.