- Diversion tunnel<br />

civil works are in<br />

progress as per<br />

schedule.<br />

Vindhyachal-III (2x500 MW), Madhya Pradesh<br />

Commissioning Schedule : Unit-IX (February<br />

2007)<br />

Unit-X (August<br />

2007). Efforts are<br />

on to commission<br />

both the units in<br />

the Tenth plan.<br />

Present Status : Main Plant contract<br />

awarded to BHEL<br />

in March 2003. Civil<br />

works for main<br />

plant and Boiler<br />

erection are in<br />

progress as per<br />

schedule.<br />

Kahalgaon Stage-II, Phase-I (2x500 MW), Bihar<br />

Commissioning Schedule : Unit-V (November<br />

2006)<br />

Unit-VI (May 2007)<br />

Efforts are on to<br />

commission all the<br />

units in the Tenth<br />

plan.<br />

Present Status – Phase-I : Investment approval<br />

(2x500 MW) accorded in July<br />

2003. Main Plant<br />

award to BHEL<br />

Phase-II (1x500 MW) :<br />

completed in August<br />

2003. Civil and<br />

Structural activities<br />

at site have been<br />

taken up.<br />

Unit-VII (Mar’2007)<br />

LOI has been<br />

placed on M/s<br />

BHEL in Dec’2003<br />

pending MoEF<br />

clearance, which is<br />

awaited.<br />

Sipat-II (2x500 MW), Chhatisgarh<br />

Commissioning Schedule : Unit-IV (June’2007)<br />

Unit-V (Dec’2007)<br />

Efforts are on to<br />

commission both<br />

the units in the<br />

Tenth plan.<br />

Present Status : LOI has been<br />

placed on M/s.<br />

BHEL in Dec’2003<br />

pending MOEF<br />

clearance which is<br />

a w a i t e d .<br />

Excavation work for<br />

Boiler foundations<br />

has been taken up.<br />

Unchahar-III (1x210 MW), Uttar Pradesh<br />

Commissioning Schedule : Unit-V (Sept’2006)<br />

Present Status : LOI was placed on<br />

M/s. BHEL in<br />

Dec’03. MOEF<br />

clearance received<br />

in Mar’2004 and<br />

LOA has been<br />

released to BHEL.<br />

Piling work has<br />

been started at site.<br />

B) NEW PROJECTS<br />

a NEW Project <strong>of</strong> total capacity 1980 MW<br />

have been accorded investment approval:<br />

Sl. Projects Capacity<br />

No. (Location) (MW)<br />

1. Sipat Stage-I<br />

(Chhattisgarh)<br />

1980 (3x660)<br />

Also the main plant award for Sipat Stage-<br />

I (3 X 660 MW) TG package has been<br />

placed on 6th April 2004 and award for SG<br />

package has been placed on 15th b.<br />

April<br />

2004.<br />

The following new projects with a total<br />

capacity <strong>of</strong> 4550 MW are under<br />

consideration and for which action for<br />

procurement <strong>of</strong> LNG / Natural Gas has been<br />

taken up on International Competitive Bidding<br />

basis. Implementation <strong>of</strong> these projects is,<br />

however, subject to availability <strong>of</strong> LNG / Gas<br />

in a suitable time frame, at reasonable price/<br />

terms also acceptable to the beneficiary<br />

states.<br />

Sl.No. Projects/ Capacity<br />

Location (MW)<br />

1. Kawas Stage-II/(Gujarat) 1300<br />

2. Gandhar Stage-II/(Gujarat) 1300<br />

3. Kayamkulam –II (Kerala) 1950<br />

Hydro <strong>Power</strong> Projects<br />

Construction <strong>of</strong> Koldam Hydroelectric <strong>Power</strong><br />

Project (4x200 MW) in Himachal Pradesh is<br />

progressing as per schedule. Award for Main<br />

Dam, Spillway & <strong>Power</strong> In-take Package for<br />

Koldam project (800 MW) placed in December<br />

67