58<br />
Annexure - II<br />
Details <strong>of</strong> Schemes cleared techno-economically by CEA during 1.4.2003 - 31.3.2004<br />
HYDRO SCHEMES<br />
Sl.No. Name <strong>of</strong> Scheme/State/ Installed Estimated Cost Date <strong>of</strong> CEA<br />
Executing Agency Capacity(MW) Clearance<br />
1. Kishanganga HEP in J&K 3x110 US$3.5 M 6.8.03(TEA)<br />
by NHPC =330 +Rs.3169.52 Crs.<br />
=Rs.3186.32 Crs.<br />
(Present Day Cost)<br />
(1/03 PL)<br />
2. Chamera HEP III in H.P. 3x77 US$3.708 M 10.10.03<br />
by NHPC =231 +Rs.1346.47 Crs.<br />
=Rs.1364.01 Crs.<br />
(Present Day Cost)<br />
(4/03 PL)<br />
3. Parbati HEP St. III in H.P 4x130 US$12.54 M 12.11.03<br />
by NHPC =520 +Rs.2170.69 Crs.<br />
=Rs.2228.41 Crs.<br />
(Present Day Cost)<br />
(7/03 PL)<br />
4. Teesta Low Dam Stage-IV 4x40<br />
HEP in W.B. by NHPC =160 Rs. 998.36 Cr.<br />
(Present Day Cost)<br />
(8/03 PL)<br />
23.12.03<br />
5. Uri Stage II HEP in J&K 4x60 US$10.393 M 11.2.04(TEA)<br />
by NHPC =240 +Rs.1647.92 Crs.<br />
=Rs. 1695.73 Crs.<br />
(Present Day Cost)<br />
(7/03 PL)<br />
6. Nimoo Bazgo HEP in J&K 3x15 Rs.631.54 Crs. 16.3.04(TEA)<br />
by NHPC =45 (Present Day Cost)<br />
(9/03 PL)<br />
SUB-TOTAL (HYDRO) 1526 MW<br />
THERMAL SCHEMES<br />
Sl.No.Name <strong>of</strong> Scheme/State/ Installed Estimated Cost Date <strong>of</strong> CEA<br />
Executing Agency Capacity(MW) Clearance<br />
1. Monarchek CCGT Project 280 US$99.55 M 25.4.03<br />
in Tripura by NEEPCO +Rs.504.156 Crs.<br />
(Revised Proposal) = Rs. 977.019 Crs.<br />
(Completion Cost)<br />
2. Kahalgaon STPP – St. II, 2x500 US$ 373.548 M 13.6.03<br />
Phase-I in Bihar by NTPC =1000 +Rs.2118.577 Crs.<br />
=Rs.3930.285 Crs.<br />
(Present Day Cost)<br />
(4th Qtr.2002 PL)<br />
3. Paras TPS Expansion in 1x250 Rs. 1026.70 Crs. 13.6.03<br />
Maharashtra by MSEB =250 (Completion Cost)<br />
Sub Total (T) 1530 MW<br />
GRAND Total (H+T) 3056 MW<br />
Note : TEC meetings for thermal projects were held as per E(S) Act, 1948 before The<br />
Electricity Act, 2003 i.e. 10.6.03. Now TEC <strong>of</strong> CEA is not required for thermal Schemes<br />
as per The Electricity Act, 2003.