04.08.2013 Views

Untitled - Ministry of Power

Untitled - Ministry of Power

Untitled - Ministry of Power

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

106<br />

identified for R&M/LE and PHS Unit # II and<br />

PHS Unit # I.<br />

The RM&U work <strong>of</strong> MHS Unit # II by ALSTOM<br />

– BHEL consortium is in advanced stage <strong>of</strong><br />

completion. A portion <strong>of</strong> additional imported<br />

items have reached site. Balance materials<br />

are yet to be delivered by Consortium.<br />

Completion date has been further extended<br />

upto 30.06.2004.<br />

For RLA study <strong>of</strong> PHS Unit # I, re-tendering<br />

has been done after inclusion <strong>of</strong> additional<br />

vendors, as suggested by the consultant.<br />

Action for R&M/LE <strong>of</strong> MHS units # I & III will<br />

be taken after observing the performance <strong>of</strong><br />

MHS unit # II.<br />

Capacity Addition Programme during 10th Plan<br />

DVC has taken up capacity addition <strong>of</strong> 2210 MW during 10th Plan, brief status <strong>of</strong> which is indicated<br />

below:<br />

Sl No Project Capacity Target COD Brief Status<br />

1 Mejia TPS Extn. 1x210 MW Sept 2004 EPC Contractor: M/s BHEL. Major activities<br />

Unit # IV completed: Lifting <strong>of</strong> Boiler Drum, Hydro test<br />

(drainable), TG Casting etc. Activities in<br />

progress: Boiler, TG erection etc. BHEL is<br />

being pursued for supply <strong>of</strong> balance plant &<br />

equipment, which are delayed.<br />

2 Mejia TPS Extn. 2x250 MW 2006-07 All clearances obtained. EPC contract through<br />

Unit # V & VI negotiation with BHEL & PPA with beneficiaries<br />

under finalisation.<br />

3 Chandrapura TPS 2x250 MW 2006-07 MOEF clearance awaited.Engagement <strong>of</strong><br />

Extn. Unit # VII Consultant for EPC contract through ICB route:<br />

& VIII Techno-commercial bids opened on 27.01.04 are<br />

under scrutiny. COD is likely to slip.<br />

4 Maithon Right 4x250 MW 2006-07 Land acquisition in progress. The consultant is<br />

Bank TPS* being appointed for finalization <strong>of</strong> EPC contract<br />

through ICB route.<br />

* Implementation through Maithon <strong>Power</strong> Ltd (MPL), presently a wholly owned subsidiary <strong>of</strong> DVC after<br />

exit <strong>of</strong> erstwhile partner BSES (presently Reliance Energy). DVC is currently on the look out for<br />

another strategic joint venture partner for MPL.<br />

TRANSMISSION & DISTRIBUTION<br />

Matching with generation capacity addition,<br />

expansion <strong>of</strong> existing T&D network <strong>of</strong> DVC during<br />

10th Plan has been taken up as per the<br />

programme detailed below.<br />

T&D addition programme during 10th Plan<br />

220 KV Sub-stations 11 nos<br />

220 KV Lines 1686 ckt km<br />

132 KV Sub-stations 4 nos<br />

132 KV Lines 74 ckt km<br />

FLOOD CONTROL & WATER RESOURCE<br />

MANAGEMENT<br />

FLOOD CONTROL<br />

As per the unified development scheme <strong>of</strong><br />

Damodar basin submitted by Mr. W.A. Voorduin<br />

in August 1944, eight Storage Reservoirs viz,<br />

Maithon, Deolbari (near Balpahari), Tilaiya, Aiyar<br />

(near Tenughat), Bermo, Bokaro, Konar and<br />

Solanpur (near Panchet) were to be built on river<br />

Damodar and its tributaries with the main<br />

objectives <strong>of</strong> flood control, irrigation, domestic<br />

and industrial water supply and hydel power<br />

generation.<br />

At the first stage <strong>of</strong> implementation, four multipurpose<br />

Dams at Maithon, Panchet, Tilaiya and<br />

Konar have been constructed. But the designed<br />

storage levels could not be achieved due to<br />

constraint in acquiring the required land from the<br />

State Governments in respect <strong>of</strong> Maithon and<br />

Panchet reservoirs. In the first phase, total flood<br />

reserve capacity <strong>of</strong> 1.05 million acre-ft. could be<br />

arranged.<br />

However, even with the partial implementation <strong>of</strong><br />

the scheme, DVC over the years has been able<br />

to play a vital role in moderation <strong>of</strong> the floods to<br />

a great extent.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!