SQ254 Heat Exchanger<br />
1.4 Function description of the heat exchanger<br />
The device is designed to operate the gas sampling probe and the sample gas at a temperature above the dew<br />
point of acids (appr. 130 °C).<br />
During the start up the coolant is bypassed by the three-way valve directly to the gas-sampling probe. After<br />
exceeding the setpoint of the minimum temperature for the closed position of the three-way-valve, the coolant is<br />
directed through the heat exchanger. This method ensures a short heating-up-time of the coolant. Sample gas will<br />
not be taken below the minimum temperature. A cooling fan is switched on at coolant temperatures above 180°C<br />
to force the cooling of the radiator. If the coolant temperatures drops below 180°C the cooling fan is switched off<br />
again.<br />
The level switch (6) monitors the “level minimum” in the expansion vessel. In case of low level of the liquid the<br />
circulating pump is switched off.<br />
For troubleshooting please refer to page 7, “level minimum”.<br />
The flow meter (4) monitors the flow of the coolant. If the minimum flow is less than the minimum for more than 5<br />
sec, the circulation pump is switched off and an alarm is generated. For troubleshooting please refer to page 7,<br />
“Flow”.<br />
For thermal overload protection the probe is being retracted from the kiln at coolant temperatures more than<br />
220°C.<br />
For troubleshooting please refer to page 7, “Exceed temperature”.<br />
Faults are indicated on the signal lamps on the cabinet. For further utilization it can be wired to a control system<br />
by means of potential free contacts.(wiring diagram G 3302-A3254-S004)<br />
Copyright ® SIEMENS Page 78 04/04