SQ254 Heat Exchanger<br />
2. Installation<br />
2.1 Installation of the heat exchanger<br />
The installation platform has to be even and must endure a weight of estimated 400 kg/m 2 . The device should be<br />
protected against direct influence of weather (snow, rain, sun). It is filled up with heat transfer liquid ex works.<br />
The connection pieces for the cooling tubes are sealed with blind flanges. The flow direction is marked by means<br />
of arrows. After removal of the blind flanges the flexible hoses have to be connected between the sample probe<br />
and the heat exchanger. The bleed valves (15) have to be mounted at the highest point of the flexible hose. The<br />
3000mm hoses are for the connection between the sample probe and the bleed valves. The bleed valves are<br />
connected to the heat exchanger by means of the 1500mm hoses.<br />
The level indicator on the expansion vessel (5) is adjusted to a “cold level” of 87mm. The switch point of the level<br />
switch is adjusted to a minimum level of 85 mm, measured from the bottom of the expansion vessel.<br />
2.2 Electrical connection<br />
The electric connection has to be carried out according to the national standards at the installation site.<br />
2.3 Filling up the heat exchanger with cooling liquid<br />
Perform the following steps:<br />
1) close the bleed valves (15) before filling up the cooling liquid<br />
2) remove the screw plug (5) at the expansion vessel<br />
3) fill in the cooling liquid up to estimated ¾ of the expansion vessel<br />
4) close the expansion vessel with the screw plug<br />
5) open the stop valve (14) completely<br />
6) set the main switch into the “ON” position<br />
7) press S1 to start the circulation pump<br />
8) observe the coolant level through the inspection glass<br />
9) press S2 to stop the circulation pump, when the coolant level drops below ¼ of the<br />
expansion vessel<br />
10) repeat steps 2 to 9 until the filling level stabilize to “LEVEL COLD”<br />
11) carefully open the bleed valves (15) so that air and bubbles can escape<br />
12) open and close the bleed valves in short terms until air is completely escaped<br />
13) observe the flow meter. Stable flow indicates the bubble free cooling circuit<br />
14) Check the “COLD LEVEL” again and perform steps 2 to 13, if required<br />
Excess coolant can be drained by means of the valve at the bottom of the heat exchanger.<br />
Check the sieve in the filter neck after some time of operation and clean it, if necessary.<br />