\\MABOS\projects\1<strong>13</strong>81.00\reports\Article80\Expand<br />
ed_PNF\03_Transportation_FINAL.doc<br />
Vanasse Hangen Brustlin, Inc.<br />
The Point, <strong>Boston</strong><br />
to future traffic conditions resulting from regional growth as well as traffic generated by specific planned<br />
projects that are expected to affect the local roadway network.<br />
Background Growth<br />
A background growth rate of half a percent per year was applied to the traffic volumes. This growth rate is<br />
consistent with recent traffic studies for other developments in the Fenway and LMA. In addition to the<br />
background growth rate, traffic projections and infrastructure changes for several specific projects were<br />
incorporated in the development of No Build Condition. These include the following development projects:<br />
Landmark Center North<br />
Fenway Center (Parcel 7)<br />
121 Brookline Avenue (Research and Development)<br />
Massachusetts Mental Health Center <strong>Redevelopment</strong><br />
Dana-Farber Cancer Institute’s Center for Cancer Care<br />
Children’s Hospital <strong>Boston</strong> – 57 Binney Street Project<br />
Longwood Center (formerly Joslin Diabetes Center Expansion Project)<br />
Longwood Research Institute (formerly Longwood North Research Center)<br />
The Fenway Triangle Mixed Use Project<br />
The Winsor School Expansion and Research Building<br />
1282 Boylston Street Mixed-Use Project<br />
The infrastructure projects include the following:<br />
Boylston Street Reconstruction Project<br />
New Street between Boylston Street and Van Ness Street<br />
Two-way Van Ness Street as part of the Fenway Triangle Mixed Use Project<br />
Army Corp of Engineer’s Muddy River Project<br />
The 2017 No-Build projections incorporate the planned New Street that will connect Van Ness Street to<br />
Boylston Street midblock between Kilmarnock Street and Yawkey Way. This street will provide two-way<br />
travel and will be constructed as part of the recently approved Fenway Triangle Mixed-Use Project. In<br />
addition, operations on the currently underutilized Van Ness Street will modified to allow two-way travel<br />
with the construction of the Fenway Triangle Mixed Use Project. This change has been incorporated into the<br />
No-Build analysis. As a result, traffic on Kilmarnock Street is reduced in the No-Build Condition because Van<br />
Ness Street traffic will disperse in the neighborhood rather than be funneled onto Kilmarnock Street.<br />
Also included in the 2017 No Build Condition is the Army Corp of Engineer’s proposed Muddy River Project<br />
at the Sear’s Rotary. As part of this project, the existing jug handle will be eliminated and left-turns from<br />
Brookline Avenue eastbound onto Park Drive will be permitted. In addition, eastbound movements from the<br />
Riverway will be provided with a direct connection to Park Drive so that traffic destined towards Audubon<br />
Circle will no longer have to circulate through the Brookline Avenue portion of the Sear’s Rotary.<br />
Figures 3.11 and 3.12 present the 2017 No-Build Condition traffic volumes accounting for background growth<br />
and planned infrastructure changes for the morning and evening peak hours, respectively.<br />
3-10 Transportation