(4) reasonable evidence that the Work cannot be completed for the unpaid balance <strong>of</strong> the<br />
Contract Sum;<br />
(5) damage to the <strong>College</strong> or a separate contractor;<br />
(6) reasonable evidence that the Work will not be completed within the Contract Time, and<br />
that the unpaid balance would not be adequate to cover actual or liquidated damages for<br />
the anticipated delay; or<br />
(7) repeated failure to carry out the Work in accordance with the Contract Documents.<br />
10.1.15 When the above reasons for withholding certification are removed, certification will be made for<br />
amounts previously withheld.<br />
10.1.16 The Contracting Officer or its authorized representatives may reduce line items previously<br />
approved and paid should it be found that the work represented as complete is rejected or not complete. Held<br />
retainage will not serve for these discoveries.<br />
10.1.17 If the Contracting Officer withholds certification for payment under this article, the <strong>College</strong> may,<br />
at its sole option, issue joint checks to the Contractor and to any Subcontractor or material or equipment suppliers to<br />
whom the Contractor failed to make payment for Work properly performed or material or equipment suitably<br />
delivered.<br />
10.1.18 Withholding Payment for Non-Delivery <strong>of</strong> Data:<br />
(a) If technical data such as "As Built" drawings, reports, spare parts lists,<br />
repair parts lists, or the like, or instructions books (including operational and<br />
maintenance manuals), or any part there<strong>of</strong>, are not delivered within the time<br />
specified by this contract or are deficient upon delivery, the Contracting Officer<br />
shall at its discretion, withhold from each invoice a percentage (in addition to any<br />
other retainage required by the Contract) or the contract price in accordance with<br />
the following table.<br />
When total contract<br />
Percentage to be<br />
price is withheld is .<br />
Less than $250,000<br />
5% <strong>of</strong> total contract<br />
$250,000 to $1,000,000 2% <strong>of</strong> total contract<br />
Over $1,000,000<br />
1% <strong>of</strong> total contract<br />
(b) The withholding <strong>of</strong> any sums pursuant to this Article shall not be<br />
construed as, or constitute in any manner, a waiver by the <strong>College</strong> <strong>of</strong> the<br />
Contractor's obligation to furnish the data required under this contract. In the event<br />
the Contractor fails to furnish these items, the <strong>College</strong> shall have those rights and<br />
remedies provided by law and pursuant to this contract in addition to, and not in<br />
lieu <strong>of</strong>, the sums withheld in accordance with this Article.<br />
(c) Separate line items based on corresponding percentage representing the<br />
above data shall be included in the schedule <strong>of</strong> values as follows:<br />
As-Built Drawings<br />
Closeout Documents<br />
10.2 Application for Payments<br />
10.2.1 An Application for Payment is a written request for payment under the Contract for supplies delivered<br />
or for service rendered. In order to be proper, an invoice must include as applicable the following:<br />
(a)<br />
Total Amount - Payee Name and Address - Department/Agency - Payee<br />
RCNJ <strong>Project</strong> No.: 09-270.1C - 43 -