14.2.8 Where the cost <strong>of</strong> property made obsolete or excess as a result <strong>of</strong> a change is included in the<br />
Contractor's request for adjustment, the Contracting Officer shall have the right to prescribe the manner <strong>of</strong> deposition <strong>of</strong><br />
such property.<br />
14.2.9 Failure to agree to any adjustment shall be a dispute concerning a question <strong>of</strong> fact within the meaning<br />
<strong>of</strong> the Article <strong>of</strong> this contract entitled "Contracting Officer Hearing." However, nothing in this Article shall excuse the<br />
Contractor from proceeding with the contract as changed.<br />
14.2.10 Contractor must submit a request for contract adjustment on the provided form by the Construction<br />
Manager at the project kick-<strong>of</strong>f meeting. Request’s not on the required form will be returned without action.<br />