SECTION 01 31 00 – PROJECT ADMINISTRATION AND PROCEDURES<br />
PART 1 - GENERAL<br />
1.1 SUMMARY<br />
A. This Section specifies administrative and supervisory requirements necessary for <strong>Project</strong> coordination<br />
including, but not necessarily limited to:<br />
1. <strong>Project</strong> Administration.<br />
2. Requests for Information.<br />
3. Submittals.<br />
1.2 PROJECT ADMINISTRATION<br />
A. All project related correspondence is to be issued to the Construction Manager, with carbon copies to<br />
the Architect.<br />
B. The Contractor is to submit construction daily reports to the Construction Manager at the end <strong>of</strong> each<br />
week. Daily reports must include the date, weather, subcontractors/vendors onsite, manpower count,<br />
equipment onsite, material deliveries, work description by area, etc. Payment applications will not be<br />
processed if daily reports are not submitted as required.<br />
1.3 REQUESTS FOR INFORMATION<br />
A. The Contractor is to prepare and submit a Request for Information (RFI) to the Construction Manager<br />
for action when a clarification and/or additional information are required to perform an activity <strong>of</strong> work.<br />
B. The request must include a drawing and/or specification reference when applicable and must also<br />
include a proposed solution for review by the Architect. Requests not provided with a recommended<br />
solution, if applicable, will be returned to the Contractor with no action until such recommendation is<br />
provided.<br />
C. The Architect will endeavor to respond to requests within (5) business days. Should a response not be<br />
received within this time period by the Architect, the Contractor will not be entitled to an extension <strong>of</strong><br />
time and/or additional incurred costs.<br />
1.4 SUBMITTALS<br />
A. The Contractor is to submit resumes for assigned project managers and superintendents to the project.<br />
B. The Contractor is to submit a company safety manual prior to onsite mobilization.<br />
<strong>Ramapo</strong> <strong>College</strong> <strong>of</strong> <strong>New</strong> <strong>Jersey</strong><br />
01 31 00 PROJECT ADMINISTRATION AND PROCEDURES<br />
E-Wing Renovation for Teacher’s Education Page 1 <strong>of</strong> 1<br />
RCNJ <strong>Project</strong> No. <strong>11</strong>-<strong>210C</strong><br />
Prepared by:<br />
Cambridge Construction Management<br />
- END OF SECTION 01 31 00 -