SECTION 01 <strong>11</strong> 05 – TIME OF COMPLETION<br />
PART 1 - GENERAL<br />
1.1 PROJECT SCHEDULE<br />
A. Substantial Completion (issuance <strong>of</strong> Temporary Certificate <strong>of</strong> Occupancy), and Final<br />
Completion to the satisfaction <strong>of</strong> the <strong>College</strong>, Architect and Construction Manager shall be on or<br />
before the milestone dates set forth in the schedule below.<br />
1. Contractors can anticipate the Notice to Proceed being issued within two (2)<br />
weeks <strong>of</strong> the bid opening date.<br />
2. Contractors can anticipate construction permits being issued by the <strong>New</strong> <strong>Jersey</strong><br />
Department <strong>of</strong> Community Affairs (30) calendar days after filing permit<br />
applications<br />
B. The listed milestone dates represent the Contractor’s contractual obligations to the Owner:<br />
1. Milestone 1 – August 17, 2012: Substantial completion<br />
2. Milestone 2 – September 14, 2012 <strong>Project</strong> completion<br />
- END OF SECTION 01 <strong>11</strong> 05 -<br />
<strong>Ramapo</strong> <strong>College</strong> <strong>of</strong> <strong>New</strong> <strong>Jersey</strong><br />
01 <strong>11</strong> 05 TIME OF COMPLETION<br />
E-Wing Renovation for Teacher’s Education Page 1 <strong>of</strong> 1<br />
RCNJ <strong>Project</strong> No. <strong>11</strong>-<strong>210C</strong><br />
Prepared by:<br />
Cambridge Construction Management