tests are determined and upgrade approved by the Construction Manager.<br />
4.26 Maintenance <strong>of</strong> Construction Access Routes<br />
4.26.1 The Contractor shall be responsible for providing and maintaining unobstructed traffic lanes on the<br />
designated Construction Access Routes either shown on the Contract Drawings or reasonably required so as to perform<br />
the Work and shall provide and maintain all reasonably required safety devices. He shall provide the addition <strong>of</strong><br />
materials, their grading and compaction, the removal <strong>of</strong> snow and debris so as to provide and maintain the general<br />
serviceable condition <strong>of</strong> the access roadbed, as well as pedestrian ways.<br />
4.27 <strong>Project</strong> Sign<br />
4.27.1 The Contractor shall erect and maintain one (1) sign at the <strong>Project</strong> Site. Paintings shall be done by a<br />
pr<strong>of</strong>essional sign painter, with two (2) coats <strong>of</strong> exterior paint, colors, letter face and layout as shown. No other signs will<br />
be permitted at the Site unless otherwise authorized by the Contracting Officer. Upon completion <strong>of</strong> the <strong>Project</strong>, and<br />
when directed by the Construction Manager or the <strong>College</strong>, the Contractor shall remove the sign.<br />
4.28 Maintenance Bond<br />
4.28.1 Prior to final inspection and acceptance <strong>of</strong> the work by the Contracting Officer and its authorized<br />
representatives, the Contractor shall furnish a one year maintenance guarantee in the amount <strong>of</strong> five percent (5%) <strong>of</strong><br />
the final total contract cost, in the form <strong>of</strong> a certified check or a maintenance bond for the same amount guaranteeing<br />
faithful compliance with the guarantee noted above.<br />
4.29 Use <strong>of</strong> Premises<br />
4.29.1 The Contractor shall limit his use <strong>of</strong> the premises to construction activities in areas indicated.<br />
4.29.2 Confine operations to areas within contract limits indicated. Portions <strong>of</strong> the site beyond areas in<br />
which construction operations are indicated are not to be disturbed.<br />
4.29.3 Keep driveways and entrances serving the premises clear. Parking spaces outside <strong>of</strong> the<br />
construction area are to be available at all times to the <strong>College</strong>. Do not use these areas for parking or storage <strong>of</strong><br />
materials. Schedule deliveries to minimize impact to <strong>College</strong> operations.<br />
4.29.4 Maintain the existing building in a weather tight condition throughout the construction period.<br />
Repair damage caused by constructions operations. Take all precautions necessary to protect the building during the<br />
construction period.<br />
4.30 Operation and Maintenance <strong>Manual</strong>s<br />
4.30.1 Prepare instructions and data by personnel experienced in maintenance and operation <strong>of</strong> described<br />
products. Final payment will not be processed until submitted and approved. A total <strong>of</strong> (3) copies and an electronic<br />
version on CD are to be submitted.<br />
4.30.2 Prepare data in the form <strong>of</strong> an instructional manual.<br />
4.30.3 Binders are to be commercial quality, 8-1/2 x <strong>11</strong> inch three ring binders with durable plastic<br />
covers. When multiple binders are used, correlate data into related consistent groupings.<br />
1. Identify each binder with typed or printed title “Operation and Maintenance Instructions”,<br />
identify the project, identify subject matter <strong>of</strong> contents.<br />
2. Provide tabbed dividers for each separate product and system, with typed description <strong>of</strong><br />
product and major component parts <strong>of</strong> equipment.<br />
RCNJ <strong>Project</strong> No.: 09-270.1C - 26 -