Lismore to Mullumbimby Electricity Network ... - Essential Energy
Lismore to Mullumbimby Electricity Network ... - Essential Energy
Lismore to Mullumbimby Electricity Network ... - Essential Energy
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Group/Agency Correspondence Concern/Comment Response<br />
NSW Fire<br />
Brigade<br />
Regional North<br />
2<br />
Email received form<br />
Greg Lewis dated 25<br />
March 2010<br />
From your info supplied I would assume that Country<br />
<strong>Energy</strong>'s work in upgrading the electrical network on the Far<br />
North Coast will involve road disruptions in areas that the<br />
NSWFB Stations below, operate in.<br />
Refer Table 4.1 Roles and Responsibilities (TM.WC.05) which<br />
includes notification by fax <strong>to</strong> impacted Fire Brigade Station<br />
one week prior <strong>to</strong> commencement of road disruptions<br />
I have supplied fax numbers <strong>to</strong> those stations that may be<br />
impacted upon.<br />
Bangalow 02 66872359<br />
<strong>Mullumbimby</strong> 02 66843786<br />
Byron Bay 02 66808289<br />
Als<strong>to</strong>nville 02 66283826<br />
<strong>Lismore</strong> 02 66215481<br />
Goonellabah 02 66252390<br />
Department of<br />
Planning<br />
Letter received from<br />
Scott Jeffries dated<br />
18/05/2010<br />
Can you provide a fax <strong>to</strong> the respective station that might be<br />
impacted upon 1 week prior <strong>to</strong> the work along those roads<br />
commencing. This will give the respective Captains ample<br />
warning <strong>to</strong> inform the drivers of the traffic changes. I would<br />
also expect and hope that the local on site traffic controllers<br />
will work <strong>to</strong> assist NSWFB appliances responding <strong>to</strong><br />
emergencies around these roadworks if and when required.<br />
It should be noted that no Annex C is included in the sub-plan.<br />
Please provide a copy of Annex C with a matrix indicating<br />
how Country <strong>Energy</strong> has responded <strong>to</strong> the comments made by<br />
the relevant road authorities and emergency services, and<br />
where these responses (where included) are located within the<br />
sub-plan. A copy of Annex C must be submitted <strong>to</strong> the<br />
Department.<br />
It is noted that comments from the RTA and Byron Shire<br />
Council on the sub-plan have yet <strong>to</strong> be received. These should<br />
be pursued and included in the documentation.<br />
The Sub-Plan has been revised <strong>to</strong> include evidence of the<br />
Stakeholder consultation undertaken and any responses<br />
received. Refer Table 6.2 and Annex C Stakeholder Consultation<br />
Responses. See also this Matrix.<br />
Responses from the RTA and Byron Shire Council received –<br />
refer comments above. Responses included in Annex C.