ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA DOCUMENT NO. 0051706 TRAFFIC MANAGEMENT/FINAL/28 MAY 2010<br />
73<br />
Environmental Issue Management Strategy Responsibility Sub Plan/CE<br />
Procedure<br />
Provisions for<br />
Emergency Vehicles,<br />
Heavy Vehicles,<br />
Cyclists and<br />
Pedestrians<br />
Cyclists and Pedestrians<br />
The project activities are predominately in rural settings where cyclists and pedestrians<br />
are less likely <strong>to</strong> be encountered. However, the project activities in the vicinity of the<br />
<strong>to</strong>wnships may have an impact on these road users. In locations where pedestrians and<br />
cyclist may be encountered temporary paths and crossings will be developed <strong>to</strong> ensure<br />
safety. The designing of temporary footpaths needs <strong>to</strong> consider the following points:<br />
• Footpaths <strong>to</strong> be constructed <strong>to</strong> an all weather standard;<br />
• Adequately signposted <strong>to</strong> direct pedestrians accordingly; and<br />
• Footpaths are <strong>to</strong> be of equivalent performance <strong>to</strong> adjacent footpaths.<br />
Pedestrians are <strong>to</strong> be excluded from the works site using containment fencing.<br />
Works Coordina<strong>to</strong>r<br />
CEM2328 Traffic<br />
Control: Safety