Traffic Management Sub-Plan<br />
Uncontrolled when Printed: Revision D<br />
Date: May 2010<br />
8.4 REPORTING<br />
8.4.1 Traffic Control Plans<br />
Records are <strong>to</strong> be maintained for all traffic management measures used for the<br />
project. A record of the TCP used will be kept both on-site and on file. As the<br />
majority of the works will be short term, the following should be recorded:<br />
• the actual type, size and location of signs and devices (especially in the<br />
event of an accident);<br />
• the weather conditions;<br />
• condition of the existing road;<br />
• start and finish times of works;<br />
• inspections of work before, during and pre-closedown; and<br />
• any corrective measures or modifications made <strong>to</strong> the site.<br />
Recording of this information can be simplified by the production of a daily<br />
checklist. A generic RTA (2003) daily checklist pro forma that would be<br />
suitable for recording daily conditions is provided in Annex B. Complimenting<br />
any such daily recording with pho<strong>to</strong>graphs is recommended and may form a<br />
useful source of evidence in the event of an accident and proceeding legal<br />
action. WorkCover reporting procedures will be followed and any incidents<br />
reported immediately.<br />
8.4.2 Reporting<br />
Environmental moni<strong>to</strong>ring will be reported quarterly in accordance with the<br />
Project CEMP, Country <strong>Energy</strong>’s CEM7022 Environmental Operations Manual<br />
and Country <strong>Energy</strong>’s Procedures.<br />
Records shall be kept during the implementation and review of this Sub-Plan<br />
with a copy kept at the Project site or in a suitable location and subsequently<br />
for five years after the completion of the Project.<br />
Country <strong>Energy</strong> procedure CEPG1060 – Records Management will be<br />
implemented during the implementation of this Sub-Plan.<br />
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA DOCUMENT NO. 0051706 TRAFFIC MANAGEMENT/FINAL/28 MAY 2010<br />