Traffic Management Sub-Plan<br />
Uncontrolled when Printed: Revision D<br />
Date: May 2010<br />
5.13 PACIFIC HIGHWAY UPGRADE<br />
The Pacific Highway upgrade project is currently under construction <strong>to</strong> the<br />
west of Ewingsdale, travelling south through <strong>to</strong> west of Ballina. This<br />
potentially has significant impacts <strong>to</strong> the transmission line project works due<br />
<strong>to</strong> the alteration of existing road networks and traffic conditions and large<br />
construction areas that may impact access <strong>to</strong> the transmission line <strong>to</strong> be<br />
upgraded. Near Ballina, the transmission line is <strong>to</strong> be upgraded in several<br />
locations in the immediate vicinity of the Pacific Highway project area. Coordination<br />
with the RTA and relevant contrac<strong>to</strong>rs will be essential when in<br />
these locations <strong>to</strong> ensure the progression of the project is not hampered.<br />
5.14 ALSTONVILLE BYPASS<br />
The Als<strong>to</strong>nville Bypass is 6.2km of roadway between Als<strong>to</strong>nville and<br />
Wollongbar. The bypass will commence at Sneaths Road Wollongbar and will<br />
rejoin the Bruxner Highway at the Tropical Fruit Research Station at Perrys<br />
Hill, east of Als<strong>to</strong>nville. Construction activities commenced in mid 2009 and<br />
are continuing at present. The construction activities have the potential <strong>to</strong><br />
interact with the electricity upgrade project in the areas between Wardell<br />
Road and Teven Road (See Figure 5.7). On-going consultation with the RTA<br />
and relevant contrac<strong>to</strong>rs prior <strong>to</strong> and throughout the project construction<br />
works is recommended.<br />