Step 2: Perform a field investigation to evaluate the primarybuilding envelope elements, rooftop equipment, and structuralsystem elements, to determine if the facility was generallyconstructed as indicated on the original contract drawings.As part of the investigation, the primary elements should bechecked for deterioration. Load path continuity should also bechecked.If the results of either step indicate the need for remedial work,see Section 3.6.MAKING CRITICAL FACILITIES SAFE FROM High Wind3-31