13.07.2015 Views

47.5 MB - The Whole Building Design Guide

47.5 MB - The Whole Building Design Guide

47.5 MB - The Whole Building Design Guide

SHOW MORE
SHOW LESS
  • No tags were found...

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Mechanically attached single-ply membranes: It is recommended thatconductors be placed parallel to, and within 8 inches of, membranefastener rows. Where the conductor falls between or isperpendicular to membrane fastener rows, install an additionalrow of membrane fasteners where the conductor will be located,and install a membrane cover-strip over the membrane fasteners.Place the conductor over the cover-strip and secure the conductoras recommended above.By following the above recommendations, additional rows ofmembrane fasteners (beyond those needed to attach the membrane)may be needed to accommodate the layout of theconductors. <strong>The</strong> additional membrane fasteners and coverstripshould be coordinated with, and installed by, the roofingcontractor.Standing seam metal roofs: It is recommended that pre-manufactured,mechanically attached clips that are commonly used toattach various items to roof panels be used. After anchoringthe clips to the panel ribs, the air terminal base plates and conductorconnectors are anchored to the panel clips. In lieu ofconductor connectors that have prongs, it is recommendedthat mechanically attached looped connectors be installed (seeFigure 3-97).Conductor splice connectors: In lieu of pronged splice connectors(see Figure 3-100), bolted splice connectors are recommendedbecause they provide a more reliable connection (see Figure 3-101). It is recommended that strips of flashing membrane (asrecommended above) be placed approximately 3 inches fromeither side of the splice connector to minimize conductor movementand to avoid the possibility of theconductors becoming disconnected. Toallow for observation during maintenance inspections,do not cover the connectors.It is recommended that the buildingdesigner advise the building owner tohave the LPS inspected each spring, toverify that connectors are still attached tothe roof surface, that they still engage theconductors, and that the splice connectorsare still secure. Inspections are alsorecommended after high-wind events.MAKING CRITICAL FACILITIES SAFE FROM High Wind3-119

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!