The four-stepped cornice is heavily damaged. It will be<br />

repaired / replaced in January <strong>to</strong> March 2017. 15,000<br />

veneer bricks will be ordered in Oc<strong>to</strong>ber. Taking in<strong>to</strong><br />

account the above tentative times frames, construction<br />

of the ground floor of the Char Narayan temple might<br />

start in April 2017.<br />

First level<br />

The twelve windows are not in very bad condition.<br />

About a quarter of the constitutive elements such as the<br />

cornices and the outer frames need replacement. Of the<br />

24 struts and four corner struts, only one corner strut<br />

is broken. This will be bolted and strengthened with a<br />

strap of steel on its back. The tympana are of secondary<br />

quality and must date <strong>to</strong> the repair of the temple in<br />

the 1840s. Not all tympana were preserved before the<br />

earthquake.<br />

Second level<br />

The four windows are not in very bad condition. One<br />

quarter <strong>to</strong> one fifth of the elements need repair. Eight<br />

plaques / aedicules on both sides of the windows need<br />

minor repair. The sixteen struts and four corner struts<br />

need minor repair.<br />