4<br />
POWER-UP/COMMISSIONING<br />
4.2 - POWER-UP After the Soft-Starter has been prepared it can now be<br />
powered-up:<br />
1) Check the supply voltage:<br />
Measure the line voltage and check if it is within the<br />
permitted range (rated voltage + 10% / -15%).<br />
2) Power-up the input and switch on the control voltage:<br />
Close the input circuit breaker.<br />
3) Check if the power-up has been succesful:<br />
The HMI-3P display will show:<br />
Now the Soft-Starter will run some self-diagnosis routines and<br />
if there is no problem, the display will show:<br />
Parameter Content<br />
P72 (%IN)<br />
This means that the Soft-Starter is rdy=ready to be<br />
operated.<br />
4) Follow the commissioning procedures<br />
For combination drive "A" - Operation by HMI-3P - follow<br />
Item 4.3.2.<br />
For combination drive "B" - Operation by terminals -<br />
follow Item 4.3.3.<br />
For other configurations that require the change of<br />
several parameters (different standards), read first<br />
Chapter 6 - Detailed description of the parameters.<br />
4.3 - COMMISSIONING This Section describes the commissioning of the two<br />
characteristic combination drives describe above:<br />
Combination drive "A" - Operation through HMI-3P<br />
Combination drive "B" - Operation through Terminals<br />
43<br />
Downloaded from www.Manualslib.com manuals search engine