Sterkstroom Wool and Mutton Production Project<br />
Measurable Outcome<br />
Activities/ project description<br />
Project Leader<br />
Purchase of shearing equipment<br />
Production of high grade wool<br />
• Mentor employed (contract completed)<br />
• NWGA & DoA training<br />
• Shearing shed equipment delivered<br />
• Shearing shed at Sibonile built<br />
M. Daweti<br />
Budget 2008/09 R1 000 000<br />
Key deliverables<br />
Due date June 2009<br />
Percentage Complete 100%<br />
Budget Spent R1 000 000<br />
Stakeholders/Partners<br />
Challenges<br />
High Value Cropping<br />
Shearing shed constructed<br />
NWGA, Inkwanca LM, Community<br />
None<br />
Measurable Outcome<br />
Job creation, Poverty alleviation<br />
Activities/ project description Growing crops in crop production tunnels at irrigation schemes and Tylden and Fodder production<br />
Projects. Negotiations with Thina Sinako and Africare to establish a cut flower project<br />
Project Leader<br />
M. Daweti<br />
Budget 2008/09 R1 250 000<br />
Key deliverables<br />
Tunnels constructed<br />
Due date June 2009<br />
Percentage Complete 20%<br />
Budget Spent R298 676,73<br />
Stakeholders/Partners<br />
DoA, LM, Community, Africare<br />
Challenges<br />
Delays by DoA<br />
Cabinet Lekgotla Report<br />
Measurable Outcome Timeous submission of report<br />
Activities/ project description Calling of inputs from stakeholders<br />
Project Leader<br />
M. Danyela<br />
Budget 2008/09<br />
None<br />
Key deliverables<br />
Quality report submitted<br />
Due date End June 2009<br />
Percentage Complete 100%<br />
Budget Spent<br />
None<br />
Stakeholders/Partners<br />
Sector Depts. Provincial Govts. DPLG, LMs, Communities, Civil society<br />
Challenges<br />
Non or late submission of reports by Sector Departments<br />