79. <strong>LGED</strong> has previous experience in implementing environmental management framework<br />
and has developed reasonable institutional capacity which will be further strengthened. The<br />
Project Environmental Unit headed by an Executive Engineer, which was set-up under RTIP-I,<br />
will continue to coordinate the environmental management of the project. The project will also<br />
hire the services of two Junior Environmental Specialists through Design and Supervision<br />
Consultancy and one Senior Environmental Specialist through Management Support<br />
Consultancy for environment screening/assessment, supervision and monitoring. The EIA of the<br />
rural waterways will be conducted by qualified individual environmental consultant. In addition,<br />
the integrated performance audit will cover environmental aspects of the project and in<br />
compliance with EMF/EMPs as well as World Bank safeguard policies.<br />
80. Only the maintenance works of roads which have limited and localized environmental<br />
impact are included in year one work program after environmental screening (full environmental<br />
assessment will not be required) and appropriate mitigation plan. Other components will be<br />
implemented from the second year after completion of proper environmental<br />
screening/assessment. Construction contracts will include appropriate environmental mitigation<br />
measures, satisfactory to the World Bank.<br />
G. Other Safeguards Policies Triggered (not required)<br />
81. The OP/BP 7.50 for International waterways notification requirements were to be<br />
triggered. However, an exception allowed under the policy has been obtained and affected.<br />