Issues / Risk Mitigating Actions to be taken Agency<br />

Responsible<br />

accountability Strengthen internal accountability during RTIP-II <strong>LGED</strong><br />

implementation by<br />

(a) strengthening <strong>LGED</strong>’s project management<br />

capacity with project management consultant<br />

(b) carrying out financial audits and integrated<br />

performance audits (by external independent<br />

auditors)<br />

Operationalize the M&E framework established under<br />

RTIP-I<br />

Improve processes and systems by preparing IT-ICT-<br />

MIS strategy and action plan and implementing the<br />

recommended actions with RTIP-II support<br />

Poor Quality of Service<br />

Need to improve Use Performance Management in RTIP-II with<br />

quality of works performance targets for:<br />

on project roads (a) project districts as decision criteria to continue<br />

allocating project resources during<br />

implementation; and<br />

(b) supervision consultants<br />

Carry out Integrated Performance Audit to evaluate<br />

compliance with technical specifications in civil works<br />

contracts and with environmental and social safeguards<br />

Timeline<br />

September 2012<br />

February 15 and August<br />

15 of each year<br />

Early Warning<br />

Indicators<br />

Project management consultant not recruited or with<br />

delays<br />

Auditors not selected.<br />

Audit reports not provided or with delays<br />

Delays in addressing audit objections.<br />

<strong>LGED</strong> 2 nd year Guidelines for operationalization of M&E framework not<br />

adopted.<br />

<strong>LGED</strong><br />

Within 3 rd year Lack of <strong>LGED</strong>-wide IT-ICT-MIS strategy.<br />

Agreed actions not implemented.<br />

<strong>LGED</strong><br />

Annually<br />

Semi-annually<br />

No performance targets determined for districts<br />

No annual progress reports on Performance Management<br />

Intergrated Performance Auditor not selected<br />

Audit reports not provided or with delays<br />

High number of audit observations<br />

Audit observations not addressed or with delays<br />

ISO certification not obtained<br />

Quality Assurance and Management including ISO<br />

certification<br />

3 rd year<br />

70