Issues / Risk Mitigating Actions to be taken Agency<br />
Responsible<br />
accountability Strengthen internal accountability during RTIP-II <strong>LGED</strong><br />
implementation by<br />
(a) strengthening <strong>LGED</strong>’s project management<br />
capacity with project management consultant<br />
(b) carrying out financial audits and integrated<br />
performance audits (by external independent<br />
auditors)<br />
Operationalize the M&E framework established under<br />
RTIP-I<br />
Improve processes and systems by preparing IT-ICT-<br />
MIS strategy and action plan and implementing the<br />
recommended actions with RTIP-II support<br />
Poor Quality of Service<br />
Need to improve Use Performance Management in RTIP-II with<br />
quality of works performance targets for:<br />
on project roads (a) project districts as decision criteria to continue<br />
allocating project resources during<br />
implementation; and<br />
(b) supervision consultants<br />
Carry out Integrated Performance Audit to evaluate<br />
compliance with technical specifications in civil works<br />
contracts and with environmental and social safeguards<br />
Timeline<br />
September 2012<br />
February 15 and August<br />
15 of each year<br />
Early Warning<br />
Indicators<br />
Project management consultant not recruited or with<br />
delays<br />
Auditors not selected.<br />
Audit reports not provided or with delays<br />
Delays in addressing audit objections.<br />
<strong>LGED</strong> 2 nd year Guidelines for operationalization of M&E framework not<br />
adopted.<br />
<strong>LGED</strong><br />
Within 3 rd year Lack of <strong>LGED</strong>-wide IT-ICT-MIS strategy.<br />
Agreed actions not implemented.<br />
<strong>LGED</strong><br />
Annually<br />
Semi-annually<br />
No performance targets determined for districts<br />
No annual progress reports on Performance Management<br />
Intergrated Performance Auditor not selected<br />
Audit reports not provided or with delays<br />
High number of audit observations<br />
Audit observations not addressed or with delays<br />
ISO certification not obtained<br />
Quality Assurance and Management including ISO<br />
certification<br />
3 rd year<br />
70