Annex 3: Implementation and Institutional Arrangements<br />

Bangladesh: Second Rural Transport Improvement Project (P123828)<br />

Project Implementation and Institutional Arrangements<br />

1. Project Steering Committee. A high-level empowered Project Steering Committee<br />

(PSC) will be established to provide oversight and undertake periodic review of project<br />

implementation and addressing the issues hampering the progress. Project Steering Committee,<br />

which shall be chaired by the Secretary, Local Government Division, Ministry of Local<br />

Government, Rural Development and Cooperatives, and include as members, the Director<br />

General, Local Government Division, the Chief Engineer and Additional Chief Engineer<br />

(Planning) of <strong>LGED</strong>, and representatives of the Agriculture, Water Resources and Rural<br />

Institutions Division; IMED; Finance Division, Economic Relations Division; and the Ministry<br />

of Land. Aditionally, a Project Coordinator, having the rank of Superintending Engineer, under<br />

the Chief Engineer, <strong>LGED</strong>, will be responsible for the oversight coordination and supervision of<br />

Project activities.<br />

2. The Project Management Unit (PMU) established within <strong>LGED</strong> under RTIP-I will<br />

continue to coordinate all project preparation and implementation activities for RTIP-II. The<br />

PMU will be responsible for overall implementation of the project, which includes planning,<br />

budgeting, procurement, coordination, management, and monitoring of various components. The<br />

PMU is headed by a Project Director (PD) supported by two Deputy Project Directors with the<br />

associated adequate staff, who will be based at headquarters. Further, two additional Deputy<br />

Project Directors will be based in the field supported by staff working on a full time basis on<br />

project implementation, with expertise in social, environmental, procurement and financial<br />

management. Most of this staff already has experience in implementing previous Bank’s or other<br />

similar donor assisted projects. A Project Preparation Consultant (PPC) assisted <strong>LGED</strong> in the<br />

identification of project components and design of the first year's civil works program. PMU will<br />

be supported by an international management consultant and two design and supervision<br />

consultant teams for which selection processes already have started during project preparation.<br />

3. During implementation, <strong>LGED</strong> will receive support from an internationally experienced<br />

Management Support Consultant (MSC) in the following areas:<br />

i) Project management including coordination, reporting, monitoring of progress and<br />

programs;<br />

ii) Budgetary and financial management,<br />

iii) Review of quality control and quality assurance,<br />

iv) Reviewing payment certificates if required,<br />

v) Contractual advice and settlement of disputes, claims,<br />

vi) Implementation of the safeguard management plans (environment, resettlement etc.), and<br />

vii) Design and management of a monitoring and evaluation survey of socio-economic aspects<br />

of RTIP-II.<br />

32