ENVIRONMENTAL IMPACT STUDY<br />

Rn: 03-033 CONTAINER TERMINAL PLOCE <strong>PAGE</strong>: 4<br />

D.3.2. ENVIRONMENTAL PROTECTION MEASURES DURING<br />

CONSTRUCTION<br />

D.3.2.1. REDUCTION OF NEGATIVE EFFECTS OF NOISE<br />

Implement measures for protection against effects <strong>of</strong> increased noise level:<br />

• Obtaining <strong>of</strong> opinion and approval from the competent inspection<br />

authorities for all construction works which by nature <strong>of</strong> their<br />

technological procedure and process have to be carried out continually<br />

during the day and night (and holiday).<br />

• Restriction <strong>of</strong> daily execution <strong>of</strong> works, primarily from 6 to 23 hours.<br />

• In the construction stage, the contractor has to meet the general<br />

measures <strong>of</strong> project location protection against spreading <strong>of</strong> site noise<br />

(restriction <strong>of</strong> emitted sound power which the contractor’s equipment is<br />

allowed to have).<br />

• The contractor is under obligation to prepare the site organization<br />

schedule with clear and articulate bill <strong>of</strong> quantities and specifications for<br />

implementation <strong>of</strong> environmental protection measures according to<br />

established criteria which will have to be met during construction, all in<br />

accordance with regulations, conventions and other provisions.<br />

• Supervision during execution <strong>of</strong> works, not only the technical<br />

supervision, but also periodical or permanent supervision by inspection<br />

authorities during noise measurements performed by authorized<br />

companies.<br />

• Cooperation with trans<strong>port</strong> companies which will perform trans<strong>port</strong><br />

both on arrival and departure, should be conditioned to include the most<br />

modern trans<strong>port</strong> means (both road and railway ones).<br />

D.3.2.2. REDUCTION OF NEGATIVE EFFECTS OF WASTE<br />

Implement measures for protection against effects <strong>of</strong> waste during<br />

construction:<br />

• Packaging waste should be collected separately and distinctly marked.<br />

• Municipal and other similar waste should be collected in specialpurpose<br />

containers and regularly trans<strong>port</strong>ed.<br />

D.3.2.3. REDUCTION OF NEGATIVE EFFECTS OF SEA EXCAVATION<br />

Material obtained by submarine excavation for deepening <strong>of</strong> the <strong>port</strong> basin<br />

between Quay 5 and Quay 7 should be disposed <strong>of</strong> in <strong>port</strong> area, on the<br />

location <strong>of</strong> the container terminal and on areas designed for further <strong>port</strong><br />

development.<br />

RIJEKAPROJEKT d.o.o.