Closing Work Orders<br />

To close a work order, you must do the following two things:<br />

1 Change the order’s status to Closed.<br />

You can do this by setting Close to Yes when <strong>com</strong>pleted units<br />

are received, or by using Work Order Maintenance (16.1).<br />

2 Run Work Order Accounting Close (16.21) to post variances, clear<br />

WIP, and close outstanding operations. Execute this program<br />

regularly, at least at the end of each fiscal month, for <strong>com</strong>pleted<br />

orders.<br />

The system prevents <strong>com</strong>ponent issues and work order receipts for a<br />

closed work order. If you want to process inventory for a closed work<br />

order, you must change its status back to Released.<br />

Work Order Accounting Close<br />

Work Order Accounting Close (16.21):<br />

• Completes open work order operations.<br />

• Calculates and posts work order variances for material, labor,<br />

burden, and subcontract costs.<br />

• Calculates and posts usage variances when the labor quantity<br />

used differs from the standard.<br />

For example, if it took six hours to <strong>com</strong>plete an operation<br />

scheduled for five hours, a labor usage variance of one hour is<br />

posted.<br />

• Calculates and posts rate variances for material and subcontract<br />

when cost used differs from standard cost. If the Payroll module<br />

or Actual Pay Rate Maintenance (14.13.21) is used, rate variances<br />

are also calculated for labor.<br />

For example, when the standard subcontract cost is $10 and the<br />

PO cost is $12, the subcontract rate variance is $2.<br />

• Reconciles the WIP account for closed work orders by calculating<br />

and posting method change variances for any residual variances. WIP<br />

balances cannot be changed after the work order variances are posted.<br />

• Updates current labor and subcontract costs.<br />

WORK ORDERS 121