150 <strong>MFG</strong>/<strong>PRO</strong> USER GUIDE — MANUFACTURING<br />

Fig. 8.7<br />

Line Schedule<br />

Workbench<br />

(18.22.1.10)<br />

Unlike most <strong>MFG</strong>/<strong>PRO</strong> screens, the initial entry for these records uses a<br />

scrolling window bar. To add a new record, use the insert key. This allows<br />

entry of a sequence number, item, production quantity, and due date.<br />

Determining Order Multiples<br />

The Multiple field controls the minimum divisible schedule quantity for a<br />

workbench session. The default setting of 1.00 lets you create schedules<br />

with whole integer quantities only. When set to zero, Line Schedule<br />

Workbench attempts to use all available time to build scheduled<br />

quantities. As a result, it will schedule decimal quantities if necessary.<br />

You can set Multiple to any other quantity, as needed. This is useful if you<br />

plan orders in single units and schedule in multiples. Or you can set<br />

Multiple to any meaningful decimal quantity such as 0.5. Then, you can<br />

enter schedule quantities in units of 0.5. A negative value is not allowed.<br />

You cannot change the value of Multiple on existing schedules if nondivisible<br />

quantities would result.<br />

Sequence Numbers and Due Dates<br />

The workbench uses the sequence number and due dates to resolve<br />

scheduling conflicts. When two production runs are scheduled for the<br />

same due date but there is only enough capacity for one, the system gives<br />

priority to the one with the lower sequence number. After planning the<br />

first production run and making adjustments for changeover time, it plans<br />

output for the second production run. Because the system uses finite<br />

loading, the first scheduled due date for the second production run may be<br />

later than the date originally entered.