262 <strong>MFG</strong>/<strong>PRO</strong> USER GUIDE — MANUFACTURING<br />

Actual Input<br />

Actual input is load that has been moved to the first and subsequent order<br />

operations. It is calculated for a reporting period based on move<br />

transactions entered using work order release and shop floor control<br />

functions. Actual input is determined using the following calculation:<br />

Standard Run Hours x Quantity Moved<br />

Planned Output<br />

Planned output is load calculated based on order operations scheduled to<br />

be <strong>com</strong>pleted in a reporting period. It is determined using the following<br />

calculation:<br />

Standard Setup + (Standard Run x Quantity Ordered)<br />

Actual Output<br />

Actual output is load calculated for a reporting period based on operation<br />

quantity <strong>com</strong>pleted transactions for work orders and repetitive schedules.<br />

You can report <strong>com</strong>pleted quantities for order operations using labor<br />

feedback transactions in the Shop Floor Control, Advanced Repetitive,<br />

and Repetitive modules, or using Work Order Accounting Close (16.21).<br />

Actual output is determined using the following calculation:<br />

Actual Setup + (Standard Run x Quantity Completed)<br />

Planned Queue<br />

The difference between planned input and planned output.<br />

Actual Queue<br />

The difference between actual input and actual output.