80 <strong>MFG</strong>/<strong>PRO</strong> USER GUIDE — MANUFACTURING<br />

To access and modify a joint order set, use Work Order Maintenance<br />

(16.1).<br />

Item Number. Enter the item number for a base process or a<br />

co-product.<br />

Type. Leave blank.<br />

Routing Code. Optionally, enter an alternate routing code set up for<br />

the base process in Alternate Routing Maintenance (14.15.1).<br />

BOM/Formula. Optionally, enter an alternate base process item<br />

number. To enter this field, the work order must be for a co-product,<br />

and the base process must be set up as an alternate product structure<br />

in Alternate Structure Maintenance (13.15).<br />

Adjust Co/By Order Quantities. Enter Yes or No. This field does not<br />

appear on base process work orders. If the order quantity changes,<br />

entering Yes automatically rescales all order quantities in the joint<br />

order set. The work order status must be E, A, R, or C to optionally<br />

rescale quantities. Joint order quantities are recalculated<br />

automatically when:<br />

• Order quantity changes on a joint order whose status is Firm.<br />

• Status of a work order changes from any status to Firm.<br />

• Status of a work order changes from Batch, Planned, or Firm, to<br />

Exploded, Allocated, or Released.<br />

The system calculates the quantities for joint orders from quantities<br />

entered in Co/By-Product Maintenance (15.12.1). Order quantities for<br />

a joint order set can be recalculated automatically or maintained<br />

manually, depending on the work order status.<br />

Adjust Co/By Order Dates. Enter Yes or No. This prompt does not<br />

appear on base process work orders. If the order, release, or due date<br />

changes, entering Yes resynchronizes the dates for all orders in the<br />

joint order set. The work order status must be E, A, R, or C to<br />

optionally adjust dates. Firm status orders always resynchronize the<br />

dates for all orders in the set.<br />

Default due dates for orders in a joint set are calculated using the<br />

manufacturing lead time for the base process.