REQUEST FOR PROPOSALS RFP NUMBER: 0A1031 DATE ISSUED
REQUEST FOR PROPOSALS RFP NUMBER: 0A1031 DATE ISSUED
REQUEST FOR PROPOSALS RFP NUMBER: 0A1031 DATE ISSUED
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
e furnished and installed by the Contractor no later than 24 hours following the request for<br />
replacement, at no additional cost to the ODPS.<br />
C. Notwithstanding the ODPS’ rights under the Contract to extend one or more testing periods, the<br />
DL/ID solution is required to achieve Final System Acceptance no later than 280 calendar days after<br />
Contract execution.<br />
D. Extensions, if any, to the Alpha Test, Beta/Pilot Test, or Final System Acceptance periods shall not<br />
constitute a waiver of ODPS’ rights or remedies under the Contract for breach and/or default.<br />
Extensions may only be granted at ODPS’ request.<br />
E. The ODPS will provide written confirmation following successful completion of the Alpha Test,<br />
Beta/Pilot Test, and Final Acceptance periods. Such confirmation shall not be conclusive evidence of<br />
complete conformance in all respects to the Contract specifications and other requirements, or the<br />
non-existence of potential latent defects.<br />
F. The ODPS will, and the Contractor must, maintain appropriate records documenting performance<br />
during the Alpha Test, Beta/Pilot Test, and Final System Acceptance Periods and such records shall<br />
be conclusive for purposes of determining compliance with all testing criteria and Final System<br />
Acceptance requirements.<br />
Confirmation of Final System Acceptance shall not be conclusive regarding the non-existence of<br />
latent defects. The ODPS shall be the sole judge of compliance with testing criteria and whether any<br />
failure to satisfy or pass testing criteria was due to operator error or malfunction.<br />
G. The Contractor shall not be entitled to, and the ODPS will not pay, any charges associated with the<br />
Contractor’s failure to satisfy any testing criteria, and/or any test period.<br />
H. The Contractor shall provide a proposed written test plan which shall include, but not be limited to, all<br />
necessary criteria and tests to be performed to ensure that the DL/ID solution as a whole, and all<br />
components thereof, satisfy the requirements agreed to in this <strong>RFP</strong>, a description of all phases of<br />
testing, provisions for the documentation of testing results, problem detection, and corrective<br />
measures taken to permanently address problems, and a description of the resources, including the<br />
ODPS and Contractor staffing, necessary to conduct testing. Notwithstanding the foregoing, the<br />
ODPS shall have the sole discretion to determine the test plan, including all details contained therein,<br />
that will ultimately be used in the determination of whether the DL/ID solution, and all components<br />
thereof, satisfy the requirements and desirables agreed to in this <strong>RFP</strong> (including all addenda and any<br />
resulting Contract). The Contractor must finalize and document the written test plan, with the ODPS<br />
consultation, prior to the beginning of the Alpha Test Period.<br />
System Testing and Acceptance Period – Alpha Test Period at ODPS, Shipley Building<br />
A. The Alpha Test Period will begin upon receipt of written notice and documentation from the<br />
Contractor that delivery and installation of the DL/ID solution has been completed and a system<br />
audit and successful testing during development was performed at the site demonstrating that the<br />
system meets the design/performance capabilities stipulated by the Contract.<br />
B. The Alpha Test Period must be a fully integrated system testing period, in a non-production<br />
environment, where the Contractor must successfully demonstrate all requirements of this <strong>RFP</strong><br />
(including all addenda and any resulting Contract) for 45 consecutive calendar days, or less at<br />
ODPS’ option, in order to meet acceptance.<br />
C. The Alpha Test Period must include, but not be limited to testing to confirm, to ODPS’<br />
satisfaction, that the DL/ID solution:<br />
1. Performs successfully in accordance with all requirements specified in this <strong>RFP</strong> (including all<br />
addenda and any resulting Contract).<br />
Page 46 of 115