5. Development and maintenance of a Work Breakdown Structure (WBS) to the<br />
level of detail approved by the ODPS. The WBS will contain a project<br />
schedule including:<br />
a. Task and milestone names;<br />
b. Estimates of resource requirements;<br />
c. Resource assignments;<br />
d. Scheduled start and finish dates;<br />
e. Dependencies;<br />
f. Critical path;<br />
g. Percent complete; and<br />
h. Ten working days for the ODPS to review, comment and approve<br />
deliverables. The WBS will be developed and maintained by the<br />
Contractor, using MS-Project project management software that will be<br />
supplied by the ODPS. The project schedule must be updated and<br />
communicated as part of the weekly status reports.<br />
6. Project organization;<br />
7. Key considerations and assumptions, including potential problem areas and<br />
recommended solutions; and<br />
8. Management approaches.<br />
D. Develop and maintain a risk management plan, including key risks, constraints,<br />
assumptions, planned responses, mitigation steps and any contingencies for each.<br />
E. Develop and maintain other subsidiary management plans as required by the ODPS.<br />
The subsidiary plans required will be determined by the ODPS point of contact with<br />
input from the Contractor and will include any or all of the following:<br />
1. Project Management Work Plan:<br />
a. Scope management plan;<br />
b. Schedule management plan, including a Gantt Chart for Project<br />
Management Work Plan<br />
c. Communications management plan;<br />
2. Logging and control of open issues and pending decisions.<br />
3. Attendance and presentation of project status at regularly-scheduled status<br />
meetings.<br />
4. Delivery of weekly status reports that contain, at a minimum, the following:<br />
a. Updated WBS, along with a copy of the corresponding files (e.g. MS-<br />
Project) on diskette or CD.<br />
b. Status of planned tasks, deliverables and milestones, identifying<br />
specifically, tasks, deliverables and milestones not on schedule and a<br />
resolution plan to return to the planned schedule.<br />
c. Anticipated tasks, deliverables and milestones to be completed in the<br />
next week.<br />
d. A problem tracking report that includes issues encountered, proposed<br />
resolutions and actual resolutions.<br />
e. Results of any tests.<br />
f. Proposed changes to the work plan, if any.<br />
g. Identification of Project staff (State or Contractor) assigned to specific<br />
activities.<br />