24.8 The contractor shall be responsible <strong>for</strong> injury to any body, breakage, loss or damage<br />

to the equipment, machinery, appliance or properties connected therewith, caused<br />

by the negligence & act of omission or commission by the contractor, their staff,.<br />

24.9 The contractor shall indemnify <strong>GAIL</strong> <strong>for</strong> any accidental reason etc. caused by his<br />

labour, defective workmanship etc.<br />

24.10 The contractor shall abide by the rules & regulations of the security. The<br />

contractor’s staff shall have regular uni<strong>for</strong>ms & shoes to be provided by<br />

the contractor. The contractor shall provide one pair personal safety kit<br />

consisting of two nos. of cotton shirt , two nos. of pant and one pair of<br />

industrial safety shoes to its employees every year , photo-passes to the personnel<br />

deployed by him, if any, in connection with the services contracted out<br />

herein, without which the personnel, if any deployed will not be permitted<br />

to enter <strong>GAIL</strong> premises <strong>for</strong> security reasons. The contractor is expected to<br />

maintain antecedents of all the personnel deployed <strong>for</strong> the services<br />

contracted out herein, <strong>for</strong> security and safety reasons and furnish the<br />

same when called <strong>for</strong>.<br />

24.11 Any material taken into the building or taken out from the building, shall have<br />

necessary permission from the security personnel/higher authority of the <strong>GAIL</strong>.<br />

24.12 All services are to be offered as per ISI code of practices, wherever<br />

required/applicable.<br />

24.13 Major repairing work required at service center, major overhauling and top<br />

Overhauling is not covered in this scope of the work.<br />

24.14 Any damage caused by the contractor or his personnel to the building and its<br />

equipments should be repaired/replaced by the contractor at his own cost. If the<br />

repair /replacement job is not done by the contractor within a reasonable time<br />

then, <strong>GAIL</strong> will get it done and the cost so incurred will be deducted from the<br />

contractor’s bill.<br />

24.15 <strong>GAIL</strong> will provide a suitable space <strong>for</strong> the storing of the tools and tackles, spares,<br />

Consumables of the contractor, however, contractor has to make arrangements <strong>for</strong><br />

his almirah/locker etc. <strong>for</strong> the safety of its equipments <strong>GAIL</strong> will not be<br />

responsible <strong>for</strong> any misplacement or damage or theft of the contractor’s<br />

equipments or any other articles.<br />

24.16 Water & Electricity will be provided free of cost to the contractor <strong>for</strong> the<br />

maintenance of the system.<br />

24.17 The contractor shall have the responsibility to co-ordinate control and supervise the<br />

staff and external party called to carry out maintenance job.<br />

24.18 <strong>Contract</strong>or will have to make all necessary arrangements <strong>for</strong> security & safety of his<br />

persons and work place like providing safety belts, shoes, helmets, proper<br />

illumination of work place etc.<br />

Tender/Bid Document No: <strong>GAIL</strong>/<strong>NCR</strong>/C&P/6114<br />

ARC <strong>for</strong> O&M <strong>Services</strong><br />

107