50 Transfer of title:<br />
50.1 The title of Ownership of supplies furnished by the CONTRACTOR shall not pass on to the<br />
EMPLOYER <strong>for</strong> all Supplies till the same are finally accepted by the EMPLOYER after the<br />
successful completion of PERFORMANCE TEST and GUARANTEE TEST and issue of FINAL<br />
CERTIFICATE. 50.2 However, the EMPLOYER shall have the lien on all such works per<strong>for</strong>med<br />
as soon as any advance or progressive payment is made by the EMPLOYER to the<br />
CONTRACTOR and the CONTRACTOR shall not subject these works <strong>for</strong> use other than those<br />
intended under this CONTRACT.<br />
51 Release of in<strong>for</strong>mation:<br />
51.1 The CONTRACTOR shall not communicate or use in advertising, publicity, sales releases or in<br />
any other medium, photographs, or other reproduction of the Work under this CONTRACT or<br />
description of the site dimensions, quantity , quality or other in<strong>for</strong>mation, concerning the<br />
Work unless prior written permission has been obtained from the EMPLOYER.<br />
52 Brand names:<br />
52.1 The specific reference in the SPECIFICATIONS and documents to any material by trade<br />
name, make or catalogue number shall be construed as establishing standard or quality and<br />
per<strong>for</strong>mance and not as limited competition. However, TENDERER may offer other similar<br />
equipments provided it meets the specified standard design and per<strong>for</strong>mance requirements.<br />
53 Completion of contract:<br />
53.1 Unless otherwise terminated under the provisions of any other relevant clause, this<br />
CONTRACT shall be deemed to have been completed at the expiration of the PERIOD OF<br />
LIABILITY as provided <strong>for</strong> under the CONTRACT.<br />
54 Spares:<br />
54.1 The CONTRACTOR shall furnish to the EMPLOYER all spares required <strong>for</strong> COMMISSIONING of<br />
the plants, recommendatory and/or mandatory spares, which are required essential by the<br />
manufacturer/supplier. The same shall be delivered at SITE, 3(Three) months be<strong>for</strong>e<br />
COMMISSIONING. Also the CONTRACTOR should furnish the manufacturing drawings <strong>for</strong> fast<br />
wearing spares.<br />
54.2 The CONTRACTOR guarantees the EMPLOYER that be<strong>for</strong>e the manufacturers of the<br />
equipments, plants and machineries go out of production of spare parts <strong>for</strong> the equipment<br />
furnished and erected by him, he shall give at least twelve (12) months' advance notice to the<br />
EMPLOYER, so that the latter may order his requirement of spares in one lot, if he so desires.<br />
Tender/Bid Document No: <strong>GAIL</strong>/<strong>NCR</strong>/C&P/6114<br />
ARC <strong>for</strong> O&M <strong>Services</strong><br />
56